It's been a long process, but progress is being made!
A major hang up for us was getting our arial power lines buried. They didn't run directly over the pool but were very close. While we had the yard opened up we decided to just do it.
Last night RockyMountain Power hooked our power up with the new under ground cables, so that is awesome.
Tile work and track is laid, now it's time for coping and pavers as I understand it.
Bought the tiles sight unseen. Had a certain tile in mind, ordered them, and within minutes of leaving the store my PB called me telling me it would be 12 weeks for that tile. Instead he found a similar subway tile that he could get in 2 weeks. Sure whatever. It's COVID. Get building materials anyway you can.
Tile comes in and looks awesome. Slight bevel to it and made in Japan. Pleasant surprises do happen.
Vertical lay is unusual but I think it's going to give a very clean look to the pool.
Scheduled for plaster 2 weeks out.
No heater yet, but should be coming soon. The rest of the equipment has been procured.