Well, good news! We were turned in for plaster this morning after safety inspection, electrical inspection, pool prep, and successful punch list completion this week. Being on week 21 since dig, we are thankful to be at this point! No date yet on finish, but at least we're in line.
We are still waiting on chemical tanks for the injection system, but the PB will maintain and balance chemicals until they arrive and are installed. Once pool is filled and equipment is running, the gas contractor will return to complete gas heater hookup and complete the fire bowl install.
Safety fence isn't nearly as terrible looking as we imagined it to be, but regardless of looks, we wouldn't be without it having small children.
The Shellock deck is fantastic and was worth the wait! The temperature difference in the afternoon vs the silver travertine on the spa, is definitely noticeable on bare feet with the Shellock being much cooler. We ended up having a delay in being a pallet short and thankfully a distributor near us had two pallets or we would still be waiting.
Once the pool is complete, our landscaper will finish up with 350sqft of turf on the empty side of the deck, install landscape border next to it and complete the lighting install on the rear wall.
Fingers crossed for speedy plaster and that all of the equipment functions as it should on start up!