San Antonio PB
Estimated 4-4.5 months from excavation
Contact 1/18/21
Excavation 3/17-21/21
Steel/Plumbing 4/9/21
Gunite 5/5/21
Masonry/Decking 6/23-28/21
Sundek 7/28-30/21
Pebbletec 8/12-13/21
Fill 8/13/21
Actual just under 5 months with most of the delay due to unseasonably rainy weather.