5/11/2020 update:
A good amount of progress today. Further removal of yet more dirt (and some gravel as we downsized our house patio by 2 feet).
Utility trench is mostly dug (more needs to be dug alongside the house). You can see that off to the right in the pic.
On-site crew said there’s a good amount of digging and plumbing that will be done around the sides of the pool so we were reassured that the bulge would be addressed.
Project manager still has not replied to my email regarding the bulge and other questions:
#1 lights not installed - is this preventing us from being able to fill the pool, which would help with preventing further bulge. The niches are in...
#2 where is the French drain going?
#3 what steps will be taken to mitigate against efflorescence on our natural stone?
#4 TIMELINE - haven’t been given one. We are starting week four of this project. I realize our site limitations increase time. But a guess would be good. Or in lieu of a timeline, a Work plan / list of what comes next.
Overall I’m mostly just upset at bad communication. Maybe I have unrealistic expectations.
UPDATE. Pool Builder called right after I finished this post. Maybe he’s reading my post?
They will definitely be addressing the bulge, he told me there won’t be one when things are done. Might happen just with water filling, or they may need to dig. I was satisfied with that.
They need to dig two trenches so that will be completed in the next couple of days.
Offered a vapor barrier for the patio but said it would be expensive and as they use low lime mortar it shouldn’t cause an issue.
Timeline - probably about a month until we’re using the spa... the concrete needs to cure for a couple of weeks so we may be splashing around with concrete patios before they lay the BlueStone.
I expressed my displeasure at the poor communication. Hoping things improve from here.
Feeling better now.