Our PB said (7 months into construction) that the spa was supposed to be tiered like the drawing, but the gunite people didn’t follow the plan. So, he thinks we should do a tile spillway or maybe do the stone like on the wall but flat.
Any thoughts on whether we can have it reworked to resemble the original plan or is he correct in that we need to go in a different direction?
Thanks!
Any thoughts on whether we can have it reworked to resemble the original plan or is he correct in that we need to go in a different direction?
Thanks!