Our situation is as follows: we have a 16,000 gallon pool and we signed a contract to resurface it for $16,500. This includes emptying the pool, locate/remove all hollow and deteriorated areas (up to 30 square feet), acid wash, pressure wash, apply waterproofing, apply finish, etcetera, and treat the water, with 10 year warranty. Glas tiles were billed separately ($7,000).
It turned out that the pool floor was bad and it needed an extra day of work (crew of 6; 2 drills) to remove old plaster/marcite. This was outside of the scope of the contract, and we were billed an additional $7,750. (They came around 8am and were done around 2pm.)
I thought the additional $7,750 was rather high relative to the main contract of $16,500 which includes materials (new plaster), and chemicals to treat the water, and 2-3 weeks of work by a crew of 3 (from the day of draining the pool to applying the new plaster was more than a month, although not all days were worked, and the work also included the retiling).
However, we were forced to accept the $7,750, as we mostly prepaid the $16,500 and the contractor said they would discontinue their work if we would not pay the extra amount. We paid and the project was completed.
I have tried talking with the owner. I complained about the sales process and that the additional charge is excessive. He says the $7,750 for the extra work is 'normal', but does not want to provide details as to how this is determined. As far as I know this should be mostly wages (+overhead+profit) and some wear and tear on the drills plus some dumpster fees. The contract specifies to do 'informal mediation' before I can file for court (small claims court).
We live 10-15 minutes away from the contractor's office.
My question: Is the $7,750 indeed 'normal', or is it excessive (if it is excessive, then what would be reasonable?)
It turned out that the pool floor was bad and it needed an extra day of work (crew of 6; 2 drills) to remove old plaster/marcite. This was outside of the scope of the contract, and we were billed an additional $7,750. (They came around 8am and were done around 2pm.)
I thought the additional $7,750 was rather high relative to the main contract of $16,500 which includes materials (new plaster), and chemicals to treat the water, and 2-3 weeks of work by a crew of 3 (from the day of draining the pool to applying the new plaster was more than a month, although not all days were worked, and the work also included the retiling).
However, we were forced to accept the $7,750, as we mostly prepaid the $16,500 and the contractor said they would discontinue their work if we would not pay the extra amount. We paid and the project was completed.
I have tried talking with the owner. I complained about the sales process and that the additional charge is excessive. He says the $7,750 for the extra work is 'normal', but does not want to provide details as to how this is determined. As far as I know this should be mostly wages (+overhead+profit) and some wear and tear on the drills plus some dumpster fees. The contract specifies to do 'informal mediation' before I can file for court (small claims court).
We live 10-15 minutes away from the contractor's office.
My question: Is the $7,750 indeed 'normal', or is it excessive (if it is excessive, then what would be reasonable?)