OK, well, here it goes. I will be building my own pool. I will be doing most of the building with the help of a friend that used to build pools in Georgia. The only parts I will be subing out will be the gunite and final finish. I have done as much studying as humanily possible to prepare for this and with my friend Rick's help, this adventure should have a happy ending. :-D The process is well underway. No, no digging yet, but believe me the process is well underway. I designed the pool, hired an engineer to review my drawings and sign off on them (needed that for the city building department to buy into this and give me the permit to go ahead and dig). Just getting the permits has been an education. I knew things were going too smoothly. I just about had the city permit in my hands when the first bump in the road materialized. My septic field failed!
So now, we have to have a new septic field installed before we can get the city to give me the permit to start the dig. This is necessary because whoever built this house back in 1981 decided it would be a good thing to put the septic field in the back yard. Fine idea if you never want to use your back yard for anything, bad idea if you want to put a pool there. So, now that we need a new septic field we can move it and make more room for the pool. Not a bad thing to have happen after all, just a big delay and an extra 3K I did not expect to have to spend. Ouch!
Hope to have real on the ground pics soon. New septic is going in on Tuesday, hope to have the city permit by the end of the week. I will keep in touch. Ron 8)