- Aug 17, 2009
- 186
We are aiming for a 7 ft pool- the pool is currently at 7 feet without the steel or gunite, thus really 6 ft. We hit moist clay- no actual water to be seen but the PBer worker who is in charge says we hit water. PBer hasn't said anything to me yet but I wanted a heads up before we chat.
The real problem I see is that we have a deep end dig and the bobcat cant climb out because the moist clay/dirt. That is certain as I watched the cat slip and slid as it tried to get out of the ramp.
When talking to the PBer prior to contract he said that there would be no charge if we hit water, but what are we in for.
Hand dig the last foot?
Advice.
The real problem I see is that we have a deep end dig and the bobcat cant climb out because the moist clay/dirt. That is certain as I watched the cat slip and slid as it tried to get out of the ramp.
When talking to the PBer prior to contract he said that there would be no charge if we hit water, but what are we in for.
Hand dig the last foot?
Advice.