So I have my forms up and pool dug. Forms -Approximately 16-24" above grade all around. I plan to back fill and match the height with a tall concrete deck after the forms are off.
All of the forms bracing is in the way of plumbing. I am thinking of just running my plumbing out of the forms and then connecting them together with cheap 1" pipe for pressure test. Then after Gunite, remove the forms, then plumb everything to the equipment pad.
What do you think?
Also, my return loop, I am tempted to run that in the bond beam or bench (that circles the pool), so I don't have to deal with the form bracing.
Is there a problem with that? The last pool I built, I put the return loop under my decking.
Thanks
Sent from my iPhone using Tapatalk
All of the forms bracing is in the way of plumbing. I am thinking of just running my plumbing out of the forms and then connecting them together with cheap 1" pipe for pressure test. Then after Gunite, remove the forms, then plumb everything to the equipment pad.
What do you think?
Also, my return loop, I am tempted to run that in the bond beam or bench (that circles the pool), so I don't have to deal with the form bracing.
Is there a problem with that? The last pool I built, I put the return loop under my decking.
Thanks

Sent from my iPhone using Tapatalk