We are building a new pool/spa in our back yard and expect it to be ready in Sep/Oct 2022. Repurposing this first thread for key details and tracking the timeline.
Timeline:
Timeline:
- 5/17/2022 - Contract Signed
- 6/16/2022 - Permit Issued
- 6/29/2022 - Site Prep Day
- Week of 7/11/22 - Sod strip & Pool Layout
- Week of 7/18/22 - Dig, Rebar, & Spa Plumbing (Inspection approved 7/25/22)
- Week of 8/01/22 - Gunnite, Strip & Backfill
- Week of 8/08/22 - Plumbing and Equipment Rough-In
- Week of 8/15/22 - Tile & Gas Line
- Week of 8/29/22 - Footer
- Week of 9/05/22 - Decking
- Week of 9/19/22 - Electrical, Started screen enclosure
- Week of 9/26/22 - Finished screen enclosure
- Week of 10/03/22 - Shell Clean & Bonding Agent
- Week of 10/10/22 - Pebble Finish & Fill
Last edited: