Hopefully someone can confirm what I believe to be a mistake on my part before I rip out my conduit and retrench.
I used the plumbing trenches to get my 4 pool lights and main electrical feeds back to my equipment pad and jboxes. However, the runs required from 3 to 6 90s.
I don't know why I didn't find the information sooner, but after running the conduit I found that you cannot exceed 360 degrees in any single conduit run without a pull box.
Can someone confirm?
If so, I will need to dig a new trench from my main panel directly to my ET8 and I will have to relocate my jboxes closer to the pool lights.
Can anyone advise, the jboxes will be well out of traffic areas, is it OK to mount them at the above-grade required height supported by only the Grey PVC conduit. I have all of the materials and prefer not working with steel conduit if possible.
Thanks for the help.
I used the plumbing trenches to get my 4 pool lights and main electrical feeds back to my equipment pad and jboxes. However, the runs required from 3 to 6 90s.
I don't know why I didn't find the information sooner, but after running the conduit I found that you cannot exceed 360 degrees in any single conduit run without a pull box.
Can someone confirm?
If so, I will need to dig a new trench from my main panel directly to my ET8 and I will have to relocate my jboxes closer to the pool lights.
Can anyone advise, the jboxes will be well out of traffic areas, is it OK to mount them at the above-grade required height supported by only the Grey PVC conduit. I have all of the materials and prefer not working with steel conduit if possible.
Thanks for the help.