signed contract Mid Feb.
We've been told it will be 2 months before they do masonry (tile and coping). All material is on hand, just waiting on the subcontractor.
Original completion date was Sept 30th.
Step | Date Start | Length | Date Finish |
Excavation | 6/10/21 | 4 | 6/15/21 |
Steel | 6/23/21 | 1 | 6/24/21 |
Plumbing | 7/7/21 | 2 | 7/9/21 |
Pre-Gunite Inspection | 7/12/21 | 0 | 7/12/21 |
Gunite | 7/28/21 | 0 | 7/28/21 |
We've been told it will be 2 months before they do masonry (tile and coping). All material is on hand, just waiting on the subcontractor.
Original completion date was Sept 30th.