Fiberglass Pool Build - Lead Times

crashed97tsi

Active member
Jul 1, 2021
25
Philadelphia Area, PA
Hello All,

The full history/backstory of my experience is below. The overall question is pretty simple so skip to the bottom please if you just want to see the question.

Sorry if this is in the wrong place, I am trying to confirm some information that is being told to me and my googling has come up short. My family signed a new pool contract with a local vendor in May of 2020. At the time, it was the height of the pandemic and he was fully booked for 2020 so our scheduled install date was sometime in early 2021. The main reason we went with this vendor over his competitor in the area is because he could put in the pool about 6 months earlier then other vendor at the time.

The vendor is a nice guy and seems to have been honest throughout the process, but it is clear he is over-booked, stressed out, and quite frankly an absolutely horrible communicator. I work in construction so I'm used to dealing with these types of personalities to some extent so it really doesn't bother me that much but it makes getting information painful.

The issue we are having is that the pool manufacturer allegedly is completely shutdown due to the Texas Freeze affecting the production of vinyl ester resin and has no production schedule to provide the installer, so the installer subsequently cannot provide us with an updated installation timeline. Initially on March 17th, 2021 (approximately two weeks before the ship date of our pool scheduled to be delivered to the installer on 04/05/21), we received a letter notifying us that the pool manufacturer claimed force majeure due to a vinyl ester resin shortage and that the delay in production would be a minimum of 8 weeks due to the frozen pipes / damage caused to the vinyl ester resin plant. This was easily verifiable online so we accepted it, penciled in June 5th for the approximate delivery date and moved on with our lives.

On April 17th, we received an update from the vendor/installer saying they had a phone call with the manufacturer and that production would be down at least until the end of the month with an anticipated start date of May. This still seemed within the 8 week delay timeline previously reported so I thought it was just and update to let us know they were on schedule. The letter also said he was going to move all his gunite and liner pools up to the beginning of the season so he could 100% focus on the fiberglass pools when they arrived. It also notified us of a material increase surcharge to the contract which was completely expected as the vendor was up front that this was coming. It did not provide an amount but said it would be forwarded when it was available.

Here is where I start to get a little bit nervous. I was looking on the manufacturer's website in the middle of May and I saw that they posted an update on their production issues. It was very vague but it did say clearly they were back in production as of April 30th and provided a list of material surcharges that should be expected. I took this as very good news to getting the pool at least sometime this summer so I reached out to the vendor to ask if he heard anything. I had to call, email and text him about 8 times over two weeks before he finally called me back. He was apologetic and told me he was running around like a madman. He said there had been no update from the manufacturer on our pool lead time, he only received notice of one customer's pool coming in and he had dozens on order. He could not tell me how far ahead this person was from our order which was understandable since he was not near his paperwork to check. I told him ok and that I would check in with him in 3-4 weeks.

I checked in with him earlier this week and he sent me (and about 15 other customers on a group email) another letter saying that that manufacturer is refusing to provide any production schedule due to the inconsistent deliveries of Vinyl Ester resin and the only commitment he has from them is that all pools will be manufactured this year. He referenced July 15th as the next date where he is scheduled to receive an update from the manufacturer on what pools he can expect to receive. I started looking at this installers recent reviews and saw that they were tanking. He had about 4 stars prior to the pandemic (communication was always an issue so I knew that going in) but now he is averaging 1 star with some very angry customers.

Again, I am well aware of the supply chain issues the industries are currently facing because I am experiencing them myself in the commercial construction industry, however I have never encountered anything like this to date. The manufacturer's website presents as if everything is back to normal from the freeze, and a couple competitors in the area who also carry this manufacturer do not seem to be having the same problems, at least according to their websites and online reviews. Every pool installer is 100% booked out a year and a half ahead of time at this point so they are all over-booked and stressed out. I'm trying to not hold that against them.

Which finally leads me to my question - can any installers or customers waiting for a pool out there confirm that this delayed lead time for a fiberglass pool is accurate? Based on the original delivery date of 04/05/21, a 3-4 day transit time to my house, and the 7-10 day production process of a pool, my original production slot at the factory should have been around 3/15/21 to 3/26/21. The freeze started on February 10th, 2021, so I was about 5-6 weeks away from fabrication before the freeze. Is it normal to not even have an ETA on the pool as of July 1st considering where I was in the queue? I don't think the installer is being dishonest I am just trying to get a sanity check on what I am being told.
 
Yeah, we made that same mistake!

Have you contacted the pool manufacturer to see if they can confirm the builders responses?
Excellent question. I have not done that because in my experience (again in the construction industry), factories will rarely directly deal with a consumer because they don't want the hassle. This guy can be emotional and already threatened to cancel my contract and return my deposit in September of last year because he misinterpreted one of my emails. If the factory forwards my question to him because they don't want to deal with it it's just going to sour the relationship and put the project at risk.

Eventually, I will if I have to but in the meantime I was wondering if there were any other lurkers out there who could provide some insight on their timelines and experiences with fiberglass pool installs.
 
If the factory forwards my question to him because they don't want to deal with it it's just going to sour the relationship and put the project at risk.
At this point does that really matter? You are better off cutting ties early than mid project having paid him and he not showing up.
Id call instead of emailing first, just to see If you can get some clarity.
 
  • Like
Reactions: Lanzz
I have talked with a couple PBs recently who install two different FG shells in the Chicagoland area. Both of them were told their shells are at least 4-8 weeks behind schedule. Both of the builders ordered their shells last year for this year installs and they are all waiting now. Supply of the FG materials, reduced manufacturing scheduled because of freezes and then COVID, delays in drivers for transportation, and a historical amount of new orders never seen before all led to a perfect storm. There has also been a long list of "new builders" who want to get into FG installations in my area but the shell companies are not allowing it, not enough supply for the existing customer base, no way there is room for new ones right now.

Yeah, the shell delays are there, to what extent that is with your build, I'm not sure, but not sure I'd be confident in the answer you get. On a side note, not sure I'd be comfortable working with a builder who made me feel like I can't ask questions and threatens to cancel a contract. I know its a builders marker out there, but man, I couldn't deal with that.
 
  • Like
Reactions: crashed97tsi
I contracted in March this year. I was set for August and my PB'er told me we're hitting our first 3 week delay which pushed me into September. He texted me 5 weeks later n told me we're delayed another 2 weeks n my August install is now into October.

There are major delays for these fiberglass pools. I do not get upset over it because he can not control the situation. I'll get my pool eventually. My worst case scenario is having an install next spring. I'm already bracing for it.
 
  • Like
Reactions: crashed97tsi
Yeah, the shell delays are there, to what extent that is with your build, I'm not sure, but not sure I'd be confident in the answer you get. On a side note, not sure I'd be comfortable working with a builder who made me feel like I can't ask questions and threatens to cancel a contract. I know its a builders marker out there, but man, I couldn't deal with that.
Without going into too much unnecessary detail, the dispute was around our contract. We signed it and then literally two weeks later got a formal letter from him saying prices were going up and they would be modifying the contract accordingly. I wrote an email saying we accepted the charges but I had a bit of an issue with these not being included in our base contract prepared two weeks earlier. I also told him it was my understanding that this should be the last of the material delays. All of this was in an email and when he read it he took it as an attack on his integrity that i was trying to mark him up and he didn't want to do business with me. I spoke to him on the phone and we straightened out and it hasn't been brought up since. I only write emails to him for documentation purposes now to avoid any further miscommunications. He really isn't a bad guy, he is just overwhelmed and horrible at communicating which is the main reason he is getting bad reviews right now

Thank you for the information, it sounds like what he is telling me is pretty accurate based on the people you talked to.

I contracted in March this year. I was set for August and my PB'er told me we're hitting our first 3 week delay which pushed me into September. He texted me 5 weeks later n told me we're delayed another 2 weeks n my August install is now into October.

There are major delays for these fiberglass pools. I do not get upset over it because he can not control the situation. I'll get my pool eventually. My worst case scenario is having an install next spring. I'm already bracing for it.
Great, thank you. I just wanted to make sure what he was telling me was mostly accurate. If others are experiencing this it makes me feel much better and I will just dig in an wait patiently. Thanks for the response.
 
he is just overwhelmed and horrible at communicating
Haha, sounds like a PB! Seems like most of them have pushed as many builds as they can together and seem to struggle at times. Then you get these big delays in equipment or subs and it all comes apart. Understand your point for sure, but be assured there is a big delay in shells for sure, on top of all the equipment that goes into a pool. I even tried to get a simple add on board for my Intellicenter and that was a big delay, had to borrow from Peter to pay Paul like of thing, so it is real.
 
Great, thank you. I just wanted to make sure what he was telling me was mostly accurate. If others are experiencing this it makes me feel much better and I will just dig in an wait patiently. Thanks for the response.
He's not running you around. I've been told twice now. My builder told me yesterday that he was told by the manufacturer that he can order x amount of pools for the season. Some got less than he did. He got the most in our area because he's the biggest dealer in our area for that manufacturer. He even tried to see if he could do something to speed up the process with them n they told him it was a resin shortage.

My builder is losing money over this. This is his livelihood. He is used to doing a complete pool build every 2 weeks and he's put on a tight leash now because he cant get what he needs... therefore we dont get what we want. The only thing to do is just wait it out. I've literally prepared myself for him to say, I'm sorry but I'll see you in the spring.
 

Enjoying this content?

Support TFP with a donation.

Give Support
Prepare yourself now Crashed........ once you get the shell you will *then* be into the common struggles that bind us all. Equipment, PVC, skimmers and stairs are all very hard to come by at the moment. Many are settling for whatever is available just to keep the project moving. Tons of builds are stalled mid build or pushed back altogether.

Here's somw well wishes that the rest goes smoothly once the shell arrives. :) 🤞🤞
 
I got a notice from the pool builder, the manufacturer officially pushed us back into early 2022. No commitment on even that. They are offering again to return the deposit or hold pricing for the 2022 install season. The reason we were given is because of resin allocations for the rest of the year and the manufacturing process they are deploying (setting up one type of pool and running out all of their orders).

Disappointing obviously but not unexpected. The popularity portion of the notice was kind of hard to stomach especially since this model was marketed on their Facebook page as "wildly popular" less than 3 days ago. I really hope I am not in the same situation next year in early 2022 but I guess we'll find out.

Thanks again for the feedback all, I just wanted to throw the info out there for anyone else who might find it useful.
 
Excellent question. I have not done that because in my experience (again in the construction industry), factories will rarely directly deal with a consumer because they don't want the hassle. This guy can be emotional and already threatened to cancel my contract and return my deposit in September of last year because he misinterpreted one of my emails. If the factory forwards my question to him because they don't want to deal with it it's just going to sour the relationship and put the project at risk.

Eventually, I will if I have to but in the meantime I was wondering if there were any other lurkers out there who could provide some insight on their timelines and experiences with fiberglass pool installs.
We may as well be dealing with the same PB. Our order was in later than yours but pool was ordered mid April and we were told we were 17th in line for the model we were ordering. Told by PB an early to mid June ship date, pushed to July 5th, then 5 days before pushed again to August 5th. My PB hates texting but come on man! Texts take 3-4 days to respond, I tried calling Latham and they asked for our order number so I asked him for it and explained we were trying to call and see if we could get any more info. He got ****** (he had previously told me I could cal and get more info from manufacturer if I wanted). He hadnt responded for 3 days so we called. Nice guy and very experienced but annoying business practice. As of now I assume my pool will be delayed indefinitely. Oddly my buddy’s pool (same MF) was ordered 1-2 days before ours and is in the ground and basically done. He is acting as his own GC and is using a first time PB.
 
  • Wow
Reactions: Casey
I still haven't heard anything from my builder. I'm going to assume that no news is good news.
 
Same for us we have been waiting for a year now install was supposed to be May and still not here. 3 days ago they said the pool was being loaded at plant to travel to Ontario and it got broken. Now we don't know what is going to happen
 
I’m hearing the same around here. My PB manufacturers and installs his fiberglass pools and they are having problems getting resin. They are still installing but not at their usual pace it seems.
 
My pool is scheduled to be delivered the first week of October.
 
Take your PB shopping. Show him all the Halloween stuffs being sold. Maybe you can fool him that it’s time. 😁
lol I told him it'd be nice if they got it done sooner n dropped it off early. He said, Don't hold your breathe. he's been great with communication. Always BS's with me when I text him. I got the whole month of October off so I can document the build and post here. Just waiting.
 
  • Like
Reactions: Newdude
So, we had an interesting update. Our PB called last Wednesday and said the manufacturer messed up and actually built our pool. He said he would know for sure on Monday if this was actually True.

We called Monday and he said it’s definitely made and he is just waiting transit info now. We don’t believe it to be honest but it would be par for the course, I started another project that I wasn’t intending on getting a permit for. Should be interesting conversations with the inspector when he gets here, but that’s my problem.

I will update if this thing actually arrives.
 
  • Like
Reactions: Newdude

Enjoying this content?

Support TFP with a donation.

Give Support
Thread Status
Hello , This thread has been inactive for over 60 days. New postings here are unlikely to be seen or responded to by other members. For better visibility, consider Starting A New Thread.