I am about to pull the trigger on an IG vinyl 18x36 pool w/ cantilevered concrete coping in Rochester, NY. I am planning on a broom finish concrete deck, with #57 stone or similar as backfill. The pool will be dug and backfilled in the fall, and finished in the spring, to give a good amount of time for everything to settle prior to the concrete going in. I spoke with the PB, and they said that with cantilevered concrete coping, the masons they use prefer to put it in before the liner, else it gets "tricky". When asked how they would achieve that with the split build phases, they said they would:
1) Dig, install pool walls
2) Do the concrete bottom
3) Backfill
4) Put in some sort of temporary liner (or something?), so they could partially fill the pool
5) Put up temp fencing (but no cover to the pool)
WAIT TIL SPRING
6) Pump water out of pool
7) Pour concrete deck, including cantilevered coping
8) Install liner and fill pool
Is this a standard industry build practice? Are there any red flags w/ this process? It doesn't *feel* right to me, but again, I am certainly no pool construction expert.
Thanks for any and all insights! And Happy 4th of July!
- pc
1) Dig, install pool walls
2) Do the concrete bottom
3) Backfill
4) Put in some sort of temporary liner (or something?), so they could partially fill the pool
5) Put up temp fencing (but no cover to the pool)
WAIT TIL SPRING
6) Pump water out of pool
7) Pour concrete deck, including cantilevered coping
8) Install liner and fill pool
Is this a standard industry build practice? Are there any red flags w/ this process? It doesn't *feel* right to me, but again, I am certainly no pool construction expert.
Thanks for any and all insights! And Happy 4th of July!
- pc