Hi, We contracted to have new coping, tile, and plaster done on our pool this spring. The pool company sent a subcontractor out to lay the coping. The subcontractor did the demo work on the tile and coping. Then started to do the coping and informed me the coping was the wrong size. I had to leave for an appointment and when I returned the coping had been put down anyway and was just about complete. The subcontractor said they called the pool company and sent pictures so they could see the coping was short and was told to put it down anyway. Now I have this huge gap that they want to put caulk in. I told the company this is not what we expected nor what we want. What can I do.Thanks