Another new pool in Southern California.

flynwill

Well-known member
Sep 18, 2021
374
Los Angeles, CA
Greetings:

I know this forum is mostly posts from folks with work underway but I thought I might share our nearly year long pool building adventure.

Highlights of the timeline were:

10/25/20 - Signed the contract with pool builder
5/20/21 - Excavation begins
6/16/21 - Shotcrete
10/12/21 - Plaster
10/13/21 - filled
11/18/21 - final inspection passed

Here's the PB's overhead rendering of the design:
OverHeadRender.jpg

Overall 9'x23'
Swim area 9'x16'
SPA 6'x6'
Jandy equipment
Riverflow swim current
Coverpools motorized cover

The long delay between the contract signing and the start of excavation is not the PB's fault. Before we could start pool we first need to relocate our existing underground electrical feed. A process that I had started with SCE in July of 2020, but was not actually finished until 4/30/2020.

Not long after they start excavation they run into the layer of rock.
FoundRocks.JPG

But they do get the digging completed in a few days time.
Excavation3.JPG

Next comes rebar and plumbing.
PlumbingDone1.JPG

In this picture you can see the 12" plumbing for the Riverflow, the pump itself is in the foreground with the return line to end of the pool. There are also two 12" suction lines running along the sides of the pool to grates at the back of the swimming area.

Then shotcrete
ShotCreteDone.JPG

The day after this picture was taken the forms were stripped and back-fill done. Which is good because now there was a 3 week delay before the Masons arrive and start installing the tile and coping.
Tile2.JPG

And the also build the cinderblock retaining wall that will form the base the back and side walls of our equipment shed.
Wall2.JPG

and install the decking (we went with concrete pavers a an economical choice).
pavers3.jpg

In this same timeframe the pool cover folks arrive and install stainless steel supports for the pre-cast coping pieces that will hide the cover vault.
CoverSupports.JPG

At this point the pace slowed considerably and it's not until mid August that the slab for the equipment shed is finally poured and we're ready to start that phase.
Slab2.JPG

To be continued...
 
  • Like
Reactions: BrittanyV
Continued from above...

Another two weeks wait (and I had hired a different contractor for this part as framing was not in the PB's repertoire). Framing started on 9/2
Shed1.JPG
and finished on 9/8.
Shed3.JPG

With the shed complete now we were waiting once again for the PB's plumbing crew to finish the equipment install. They finally arrive 9/24 and get the bulk done (at least enough that we can get sign-off and fill the pool).

So 10/12 plaster
Plaster1.jpg

and on 10/13 acid wash and fill:
Pool-Full.JPG

We were able to fill in about 4 hours by running a 2" hose to a hose bib at the front of the house directly from our city water supply.

A couple of pictures inside the finished equipment shed.
ShedInterior.JPG
ShedInterior2.JPG

and the finished pool
PoolLandscapeDone.JPG
 
The Riverflow works very well. I'm a pretty average 60+ year old swimmer, so I never turn it up past about 50% which seems to be it's sweet spot for supplying a nice smooth current to swim against. The 9'x13' area however is pretty much the minimum size that is possible, and if someone is swimming they basically take over the whole swimming area.
 
  • Like
Reactions: TampaKathy
Your pool came out beautiful. I like the equipment shed and how all the equipment is laid out inside. Does the shed muffle the sound of your river flow pump?
 
The shed does muffle the equipment noise a bit. We intentionally built it to be well ventilated if you look close at the pictures you'll see it's totally open between the roof rafters. The Riverflow pump itself doesn't make much noise, but the VFD does have a pretty loud cooling fan (high pitched whine). The circulation pump is very quiet except that when it starts it squeals like a stuck pig. The PB tells me "they all do that". I have it running at 1500 RPM for normal filter/circulation which gives 50GPM. The noisiest bit of gear is the heater, I can tell it's running from the other side of the yard despite the enclosure.
 
Sure the tile is Aquabella - Italian Slate Series, Naples 6x6. The pool finish is PebbleTek "Pebble Sheen" in "Blue Granite".
Be sure your tile layer properly mixes them up, as there's only three or four different patterns. Our tile guy left several places of two or three in a row of the same tile in the same orientation. We made them fix the cases of 3 in a row, but decided to not worry about the 2 in a row cases.
 
  • Like
Reactions: HappySwimming
Just one word of advice. First of all its beyond gorgeous. Now the advice part as I've noticed in the equipment pictures you have the nature 2 fusion system which has a consumable cartridge. When the cartridge depletes do not change it out for a new one as they add metals to the chemistry of the water you don't need. Just leave it in there and it'll do nothing as it won't be adding the unnecessary stuff that you can do with out.
 
Way ahead of you on that one. The original equipment spec was for the Jandy Nature2 Fusion (same box but with a tri-clor puck feeder in place of the salt cell) plus the DEL UV/Ozone unit. It was reading this forum for several weeks last summer that convinced me to request the builder to change the equipment to the SWG, and so the Fusion Soft was the choice they offered. If you look close at the first of the two shed interior pictures you'll see the "startup" mineral cartridge still sitting on the block wall behind the equipment, I never installed it and don't plan to, maybe I should offer it up on EBay?
 

Enjoying this content?

Support TFP with a donation.

Give Support
That pool came out awesome and it looked like everything went smoothly. So many times these pool build photos look like a bomb went off in the backyard, but yours seemed like the PB took the time to keep everything tidy. On a side note, the only thing (well almost the only thing) I regret was not pursuing the addition of a small bathroom, urinal, anything to use as a bathroom. I'm just nitpicking, but after having about 7 years of kids birthday parties, with kids running through the house, I wish I could go back in time. You said you are older, so that isn't the concern, but I'm getting older and I go more than the kids now.
 
but I'm getting older and I go more than the kids now.
:laughblue: Well played.

*would also like to point out that there is a short sweet spot of time between kids needing a bathroom and the grandkids starting the struggle all over again. 😁
 
That pool came out awesome and it looked like everything went smoothly. So many times these pool build photos look like a bomb went off in the backyard, but yours seemed like the PB took the time to keep everything tidy.
Ha, anything but. I just didn't post the pictures where the Masons had left trash all over the site for weeks at a time. And then there was the day I came home to find this after they left:
Plans-Dirt.JPG
That's the permit card, and the on-site (wet signature from the Engineer) plan set laying in the dirt.
 
Thread Status
Hello , This thread has been inactive for over 60 days. New postings here are unlikely to be seen or responded to by other members. For better visibility, consider Starting A New Thread.