Need help reviewing a bid

Jun 15, 2016
18
cincinnati/OH
20x40 polymer rectangle with 6" radius corners and 6'6" depth
20 mil liner
corner vinyl over step
1 8ft vinyl over bench in shallow end
2 8ft vinyl over benches in dep end
Cantilever
576 sq ft of concrete for 4' concrete deck
581 sq ft of concrete for patio ($4648)
- could change to stamped concrete for an additional $8/sq.ft
1.5 HP hayward VS pump
24" sand filter
3 returns, 2 skimmer, 1 main drain
Frog water treatment
Heat pump
Autocleaner
Mesh Safety cover
start up chemicals
skimnet, tele pole, brush, vacuum head
Individual sch 40 lines with ball valves
4" decksupports

Total: 62k
This is before electrical and fencing

I'm thinking we can adjust some cosmetics to our liking and change the price, is there anything that you would have liked to have?
- additional LED lights?
- less benches?
 
-Ditch the FROG= bad news all around! Get a Salt Water Chlorinator instead.
- What are your proposed depths?
- Skip any sort of suction or pressure cleaner and go for a robot. We can help you find a good bot probably cheaper than buying it from your builder. Check out Maytronics online.
- Use real sand, don't let them "upsell" you alternative sand products.
- Ask that each skimmer and each return be separate pipes, not tied in together.

Maddie
 
-Ditch the FROG= bad news all around! Get a Salt Water Chlorinator instead.
- What are your proposed depths?
- Skip any sort of suction or pressure cleaner and go for a robot. We can help you find a good bot probably cheaper than buying it from your builder. Check out Maytronics online.
- Use real sand, don't let them "upsell" you alternative sand products.
- Ask that each skimmer and each return be separate pipes, not tied in together.

Maddie

6'6" for depth. no diving board
 