Just set up my new 12 x 24 rectangular intex. Ground is level within 1/4 inch and the pavers are also all level within 1/4 inch. I have about 2 inches of water in it and the support legs aren't at the 13'10 and 25'10 that they're supposed to be the 13'10 side is barley sitting on my pavers which are 15" x 15" and are bang on 13'10 on centre. Before I add more water I just want to make sure this is normal and I should wait it out as I add more water and pull the supports out as it fills. If it matter the base was ground with the sod removed and dug down then levelled with about 1/4 inch to half inch of sand. Thanks for the help.