Getting Closer! May have water in the pool in a week! :lol:
Yesterday the appearance of the pool area improved dramatically. The PB hauled off all construction trash, brought in topsoil to grade the area around pool and fill flower beds, and the plaster crew came in to clean out all the trash in the pool and smooth out the gunite to prepare for plastering next week.
[attachment=0:175qwfov]pool deck and soil grading complete day 23.jpg[/attachment:175qwfov]
Today (Saturday) we expect to see the plumbing crew come in to install the pool plumbing fittings where we currently still have PVC stubs shooting out through the gunite walls and floor.
Monday we hope to see the plumbers back out for another pressure test and equipment check.
Tuesday should be drainage pipe completion and sprinkler system re-install, repair and adjust.
Then....................final inspection Wednesday in preparation for plastering and then acid wash on Wednesday/Thursday.
There is rain in the in the forecacst this week (up to 40% probability a few days) so we may not be able to move that fast, but if we do then we might have some hoses running water to fill the pool next weekend!!