16 Feb 2024 Update - Finally light at the tunnel and a tiny step forward
My favorite sub for the excavation, forming, and steel work had to back out. His partner didn't like the small single pool job combined with the risk. I have to agree there is some risk to this pool with proximity to the load bearing structures and water table. But this business is a very small community. Pretty soon they know there's this OB project that has a crazy cool pool he wants to build. I now am actually getting references from other craft labor I've met from the house build and the other pool crafts that I've requested. There's a part of big projects where the owner is out for bid on mega contracts worth hundreds of millions and greater where a part of the effort is to "sell the contractor that they should be a very strong competitor". The only have so much money to spend bidding and preparing the bid can easily be $500K or more. So there's a little bit of "reverse marketing" that the owner has to do. I feel like I'm doing a little of that now. Here are my "selling points":
- Project is fully funded and has approved building permit
- This OB builder will demonstrate payment terms that allow them to stay cash flow positive. None of the 30 day net terms they deal with on big builders that often end up net 45+ because of invoice processing problems
- I want their input on construction planning and make sure all the interfaces are understood. For example, if the steel sub hasn't worked with my gunite supplier I get the gunite sub out to the job while steel and forming are in progress... no surprises on either side of the interface. If they can't agree I decide but the decision is always made timely
- This is not an average pool and could be some marketing points to be one of the craft that built it.
So how has this worked out? It's been hard but today I finally got two great subs lined up and under contract. Now that the job seems pretty certain (weather could delay us) I went forward and built the silt fence. Easiest way to do this for me was just rent a tiller and a day laborer. Cost me about $350 total and more important I got it done this morning. Going rate for this would be about $3000 and almost impossible to schedule since the job is so small. I only had about 300' since it's only half the lot.
So there you have it, I've made a tiny amount of actual progress! I'll add photos tomorrow.
But if all goes well I should have at least the pool dug, formed, steel and plumbing in place along with 8-16 yards of #57 rock on the bottom and several pumps in place to keep it ready even if gunite is delayed. That could happen due to a 1 week trip for a medical issue on my wife. Not super serious but needs to be done.
All the subs that will be doing all the "pre-gunite" activities were here at site for final detailed construction planning. To me this is the pool version of advanced work packaging (AWP) we do for big industrial projects. We all have the plans on a big table and sequence out the actual details. It's surprising how much there is. Things like:
- Which side of the house do we bring the skid steer and excavator in on?
- Where are we gonna dump all the rock?
- Where do the diggings go and how do we transfer to the dump truck?
- Forming guy wants to start at the deep end. Can we do this?
- What is the plan for cave ins?
- What's the plan and back up if we get too much intrusion?
- Where and how much power?
- Where are the materials to be delivered?
We got all this and a lot more worked out today. Looks like we mark the pool dig Tuesday and start digging Wednesday. Gunite is on one-day standby. Pretty cool!
Chris