- Jul 21, 2012
- 4
This is my first post and would like to get some feedback on this pool quote. Equipment? Prices? Recommendations?
Thanks.
POOL 42'X18' $39,403.00
PERIMETER 115'
POOL AREA 728 SQ.FT. SURFACE AREA
EXCAVATION TYPE TRACKHOE
DEPTH 3.5'X8'
GALLONS 31,400
BEAM 1/2" 4 BARS 12"X12"-16" CONTINIOUS BEAM
SKIMMERS 2-TOTAL
DRAINS 4-TOTAL ANTI-VORTEX VGB APPROVED SAFETY DRAINS
PLUMBING RUN 40' WITH 2.5" SUCTION LINES AND INDIVIDUAL VALVES
OVERFLOW OVERFLOW TO YARD
RETURNS 6 RETURNS
GUNITE PROCESS 6"-8" 6 SACK MIX 100% NATURAL SAND
6"X6" WATERLINE TILE CHOICE OF STOCK TILE
STEPS & BENCHES 36' BENCHES $1,260.00
TANNING LEDGE 8'X18' $500.00
PLASTER WETEDGE SATIN PEBBLE $3,910.00
COPING LEUDERS RECTANGLES
CONTROLS JANDY PDA-4 REMOTE CONTROL $850.00
PUMP 2HP JANDY E-PUMP VARIABLE SPEED $475.00
FILTER JANDY VERSAFLOW 580
LIGHTS 1-JANDY WATERCOLOR LED $450.00
CLEANING SYSTEM POLARIS 280 BLACK
CHLORINATOR ZODIAC IN-GROUND FUSION CHLORINATOR
START-UP INSTRUCTION AND CHEMICAL BALANCE
START-UP KIT BRUSH, POLE, SKIMMER, TEST-KIT, & INITIAL CHEMICAL
DECKS $4,162.50
DECKING TYPE 600 SQ. FT. STANDARD SALT FINISH OR AGGREGATE
DRAINS 2-DRAIN CONNECTIONS
DRAIN LINES UP TO 75'
FEATURES $4,050.00[/b]
COLUMNS 5-24"X18" ROCK COLUMNS WITH DRAIN & DRIP IRRIGATION [b]$2,250.00
PLANTER BOWLS 3-33" CONCRETE WOK PLANTER BOWLS [b]$900.0[/b]0
FOUNTAINS 3-12" SCUPPER FOUNTAINS $900.00
CLEAN-UP $2,300.00
CLEAN UP REMOVE TRASH DEBRIS AND GRADE AROUND POOL & ACCESS
IRRIGATION REPAIR CAP & RE-ROUTE EXISTING $1,250.00
FENCE REPAIR PUT BACK ACCESS FENCE $150.00
SOD 2-PALLOTS BERMUDA SOD $900.00
ROCK CLAUSE $600 HAMMER HOOK-UP $250 PER HR. $2000 MAX. (NOT INCLUDED)
SUB-TOTAL GOOD FOR 90 DAYS $49,915.50
WINTER DISCOUNT $2,495.78
TOTAL AFTER DISCOUNT $47,419.73
REMAINING BALANCE $47,419.73
PAYMENT SCHEDULE
1ST DRAW 30% AT EXCAVATION $14,225.92
2ND DRAW 35% AT GUNITE $16,596.90
3RD DRAW 30% AT DECK SET $14,225.92
FINAL DRAW 5% AT WHEN POOL IS FULL $2,370.99
Thanks.
POOL 42'X18' $39,403.00
PERIMETER 115'
POOL AREA 728 SQ.FT. SURFACE AREA
EXCAVATION TYPE TRACKHOE
DEPTH 3.5'X8'
GALLONS 31,400
BEAM 1/2" 4 BARS 12"X12"-16" CONTINIOUS BEAM
SKIMMERS 2-TOTAL
DRAINS 4-TOTAL ANTI-VORTEX VGB APPROVED SAFETY DRAINS
PLUMBING RUN 40' WITH 2.5" SUCTION LINES AND INDIVIDUAL VALVES
OVERFLOW OVERFLOW TO YARD
RETURNS 6 RETURNS
GUNITE PROCESS 6"-8" 6 SACK MIX 100% NATURAL SAND
6"X6" WATERLINE TILE CHOICE OF STOCK TILE
STEPS & BENCHES 36' BENCHES $1,260.00
TANNING LEDGE 8'X18' $500.00
PLASTER WETEDGE SATIN PEBBLE $3,910.00
COPING LEUDERS RECTANGLES
CONTROLS JANDY PDA-4 REMOTE CONTROL $850.00
PUMP 2HP JANDY E-PUMP VARIABLE SPEED $475.00
FILTER JANDY VERSAFLOW 580
LIGHTS 1-JANDY WATERCOLOR LED $450.00
CLEANING SYSTEM POLARIS 280 BLACK
CHLORINATOR ZODIAC IN-GROUND FUSION CHLORINATOR
START-UP INSTRUCTION AND CHEMICAL BALANCE
START-UP KIT BRUSH, POLE, SKIMMER, TEST-KIT, & INITIAL CHEMICAL
DECKS $4,162.50
DECKING TYPE 600 SQ. FT. STANDARD SALT FINISH OR AGGREGATE
DRAINS 2-DRAIN CONNECTIONS
DRAIN LINES UP TO 75'
FEATURES $4,050.00[/b]
COLUMNS 5-24"X18" ROCK COLUMNS WITH DRAIN & DRIP IRRIGATION [b]$2,250.00
PLANTER BOWLS 3-33" CONCRETE WOK PLANTER BOWLS [b]$900.0[/b]0
FOUNTAINS 3-12" SCUPPER FOUNTAINS $900.00
CLEAN-UP $2,300.00
CLEAN UP REMOVE TRASH DEBRIS AND GRADE AROUND POOL & ACCESS
IRRIGATION REPAIR CAP & RE-ROUTE EXISTING $1,250.00
FENCE REPAIR PUT BACK ACCESS FENCE $150.00
SOD 2-PALLOTS BERMUDA SOD $900.00
ROCK CLAUSE $600 HAMMER HOOK-UP $250 PER HR. $2000 MAX. (NOT INCLUDED)
SUB-TOTAL GOOD FOR 90 DAYS $49,915.50
WINTER DISCOUNT $2,495.78
TOTAL AFTER DISCOUNT $47,419.73
REMAINING BALANCE $47,419.73
PAYMENT SCHEDULE
1ST DRAW 30% AT EXCAVATION $14,225.92
2ND DRAW 35% AT GUNITE $16,596.90
3RD DRAW 30% AT DECK SET $14,225.92
FINAL DRAW 5% AT WHEN POOL IS FULL $2,370.99