Finally getting around to installing our pool.
So far we have dug the hole deepest part being 2' under grade with the low side going down 7".
16 Ton worth of crusher run for the base.
Tomorrow will be getting
18- 4"x8"x16" concrete caps for the posts
16-pieces of 1" pink foam insulation.
renting a plate vibrator
Planning on a 3" base of crusher then leveling blocks on that. Then filling, leveling, tapping more crusher to the top of the blocks. OR should I get the base right and dig out the holes for the blocks? I've been goin back and forth on this in my head for the longest!
Planning on blackfilling with the excavated dirt as well. 6" french drain on top of the backfill. From what I have read the dirt needs to settle 2 years and wait till a dry week before quickly changing out the liner.
For now pump and filter will be the intex 2650 gph pump and sand filter.
Thats all for now.....
So far we have dug the hole deepest part being 2' under grade with the low side going down 7".
16 Ton worth of crusher run for the base.
Tomorrow will be getting
18- 4"x8"x16" concrete caps for the posts
16-pieces of 1" pink foam insulation.
renting a plate vibrator
Planning on a 3" base of crusher then leveling blocks on that. Then filling, leveling, tapping more crusher to the top of the blocks. OR should I get the base right and dig out the holes for the blocks? I've been goin back and forth on this in my head for the longest!
Planning on blackfilling with the excavated dirt as well. 6" french drain on top of the backfill. From what I have read the dirt needs to settle 2 years and wait till a dry week before quickly changing out the liner.
For now pump and filter will be the intex 2650 gph pump and sand filter.
Thats all for now.....