207 days!
I have read through several threads about weeping gunite and the wait for plaster. I think we have a record.
We started our pool in August during the build of our new home. To be certain there were times early on when I believe the pool could have been plastered but we weren't close to finishing on the house.
Lesson one: wait to start that pool closer to the completion of the house. Of course, we thought we would be in the house in November... but that turned into December.
We had record rainfall in those months leading up to completion of the house.
Now the pool continually weeps. The plaster company will not finish the pool unless we sign something about the weeping and that there could be a problem down the road. We won't sign that.
We are hopeful for dry and warm weather to finally get this hole plastered and filled with the kind of water we desire.
I have read through several threads about weeping gunite and the wait for plaster. I think we have a record.
We started our pool in August during the build of our new home. To be certain there were times early on when I believe the pool could have been plastered but we weren't close to finishing on the house.
Lesson one: wait to start that pool closer to the completion of the house. Of course, we thought we would be in the house in November... but that turned into December.
We had record rainfall in those months leading up to completion of the house.
Now the pool continually weeps. The plaster company will not finish the pool unless we sign something about the weeping and that there could be a problem down the road. We won't sign that.
We are hopeful for dry and warm weather to finally get this hole plastered and filled with the kind of water we desire.