So, after weeks of delays in our owner build dream....we decided to go with a pool builder. It's a family company with great references and a price that is comparable to what we hoped to spend on an O/B. The only thing that I'm not sold on is the timeline for payments. The following is what they proposed:
10% at signing
20% after excavation
15% after steel and rough plumbing
25% on day of shotcrete
5% after tile/coping
5% after pavers
10% after pebble
5% after sod
5% at start up
Does this seem fair or would you negotiate the schedule?