The summary of the tests from the pool center were:
FAC:0
TAC:0
CH:60
CYA:0
TA:100
pH:8
Copper:0
Iron:0
TDS:300
Pho:300
4600 gallon pool (15'*42"), vinyl, above ground
These results are after a 96% refill without any chemicals being added
Question being:
Was told to do the following steps:
1.) add 4fl oz of liquid muriatic acid to adjust the pH
2.) wait 4 hours
3.) add 3oz of Power Powder to adjust the FAC
4.) wait 4 hours
5.) add 2 caps of PHOSFree +
6.) wait three days then add 1/2 gallon of Leslie's Conditioner for CYA
7.) wait another 3 days
8.) add 11 pounds of soda ash for CH
Does this all sound correct and if not what do I do?
Also I will retest after adding each chemical, but what should be adjusted first and then what? I have a Taylor testing kit too
Also I have an Hayward CL200 inline, when do I add tabs to that and what setting?
Also when to shock?
Would also like to know when I can jump in...
Best,
~Allen
FAC:0
TAC:0
CH:60
CYA:0
TA:100
pH:8
Copper:0
Iron:0
TDS:300
Pho:300
4600 gallon pool (15'*42"), vinyl, above ground
These results are after a 96% refill without any chemicals being added
Question being:
Was told to do the following steps:
1.) add 4fl oz of liquid muriatic acid to adjust the pH
2.) wait 4 hours
3.) add 3oz of Power Powder to adjust the FAC
4.) wait 4 hours
5.) add 2 caps of PHOSFree +
6.) wait three days then add 1/2 gallon of Leslie's Conditioner for CYA
7.) wait another 3 days
8.) add 11 pounds of soda ash for CH
Does this all sound correct and if not what do I do?
Also I will retest after adding each chemical, but what should be adjusted first and then what? I have a Taylor testing kit too
Also I have an Hayward CL200 inline, when do I add tabs to that and what setting?
Also when to shock?
Would also like to know when I can jump in...
Best,