joshhighley
Active member
I'm reading the study guide you linked. For an AGP with a depth > 42", am I reading 680.26(B)(2)(b) correctly on page 19: I have to bury an 8 AWG bare copper conductor around the perimeter of the pool base, within 18-24" of the pool wall? I knew that rebar in a concrete pool has to be bonded, but I think this is the first I've heard of burying a bare wire around a standard AGP.
Also, if I put the equipment underneath the deck next to the pool, I also need an electrical shutoff accessible above the deck surface, per 680.12?
Also, if I put the equipment underneath the deck next to the pool, I also need an electrical shutoff accessible above the deck surface, per 680.12?