So it has been a while since I have posted. I have been a little frustrated with how long things are taking...a little to blame on the rainy weather...which I am sure directly relates to delays with sub contractor who is putting in the floor. Oh well. This has killed the initial excitement. I just need to keep in mind that we have plenty of time and it will get done before the warm weather moves in. Anyway, I will post a few updates logging the daily progress that was made. And thanks for all of the feedback concerning the lack of returns. I will definitely bring this up when the plumbing is ready to for installation.
Going back to day 13. As mentioned in my previous posts, the PB has put in well points around the deep end to try and control the ground water. They placed 6 wells at each corner around the deep end with PVC pipes connected together running to a pump. Notice the amount of water in the deep end. Unfortunately they disconnected the pump to the blind drain which was keeping water from collecting at the bottom. They soon brought out another pump to clear up this issue.
Going back to day 13. As mentioned in my previous posts, the PB has put in well points around the deep end to try and control the ground water. They placed 6 wells at each corner around the deep end with PVC pipes connected together running to a pump. Notice the amount of water in the deep end. Unfortunately they disconnected the pump to the blind drain which was keeping water from collecting at the bottom. They soon brought out another pump to clear up this issue.