Sorry for the delay in posting but thought it would be better to roll out more as it completes to speed up the post.
Here is the start of the project on April 27th:
Foundation for the pool house: May 10th
Septic line run and after second inspection due to PITA inspector: May 18th
Framing started on pool house. May 23rd
Roof done and dormers going up. Builder ordered wrong size windows for dormers..another delay. May 31st
Dormers finished and a window in. Some white trim and columns. June 4th
Windows and doors. All weather sealed. June 6th
June (Friday) 13th. Day from ****. Basement in pool house starts to flood as grading crew and pool crew start to level hot tub and grade for pavers. Luckily it was just so a minor fix, but lost the entire day for both crews. Siding done on pool house.
June 22. Rough grade and all inspections done. Day before paver crew starts.
June 23rd. Footings for spa wall and coping poured.
Got pavers? June 24th
Pool coping done and hot tub wall:
June 25th pavers starting to go down.