Hi everyone,
I am doing an owner build swimming pool in League City (south Houston), Texas. I had the pool excavated on Friday, rebar Saturday, and tomorrow plumbers are scheduled to stub out. I had gunite scheduled for Wednesday. However, the gunite company let me know that they will be unable to come because they are closing due to covid next week. So...what can I do in the mean time to keep the pool from caving in? Should I go ahead and have the plumbers come and stub out? Thank you!
I am doing an owner build swimming pool in League City (south Houston), Texas. I had the pool excavated on Friday, rebar Saturday, and tomorrow plumbers are scheduled to stub out. I had gunite scheduled for Wednesday. However, the gunite company let me know that they will be unable to come because they are closing due to covid next week. So...what can I do in the mean time to keep the pool from caving in? Should I go ahead and have the plumbers come and stub out? Thank you!