    Concrete Decking Issue!!

    So, our pool was shotcreted on Tuesday and they poured one of the decks that is going to be stone. All along, the rebar for the deck was on the ground, not blocked up, due to all the traffic in the area. My pool builder assured me that they would block it up prior to pouring it. I was there when they poured it, and looking back, I'm about 90% sure that they didn't raise the rebar prior to pouring. Therefore, the 4" concrete is over the rebar which is simply lying on the fill. My gut tells me this is a huge issue. Pool builder says they blocked it up. I really don't believe they did. What should I do? Should I insist that they tear it up and start over? Tear up a small portion to check? Please advise.

    Thanks!
    Our pool- (in process)
    38x15 Free Form Gunite (3.5'-8'), 26' Negative Edge and 7' Negative Edge spa with blower, Midnight Blue Diamondbrite, AquaLogic PS-8 control, Goldline Salt Chlorine Generator, 1.5hp Pentair 2 speed pumps (2), Pentair DE Filter, Pentair 400k BTU Heater, and BlackMaxPolaris 280 cleaner with Hayward booster pump

    build diary

  2. Back To Top    #2
    eggman's Avatar
    Join Date
    Feb 2008
    Location
    Pearland, TX - Houston suburb
    Posts
    80

    Re: Concrete Decking Issue!!

    Any way you can get under the deck on the edge ... if they didn't block it you should find rebar on the bottom of the concrete
    32x22 Free Form Gunite (3'9"- 5'3") 6'x9' Free Form Spa - 12 Jets, Blue Granite Pebblesheen, Color Logic LED Lights, AquaLogic PS-8 control, Goldline Salt Chlorine Generator, 1.5hp Tristar 2 speed pool pump, 1.5hp Tristar pump - sheer descents, 1.5hp Tristar spa pump w/1.0hp Blower, Hayward DE6020 Filter, Hayward 400K BTU Heater, Hayward Tigershark RC9990 cleaner.

  3. Back To Top    #3
    stever's Avatar
    Join Date
    Nov 2007
    Location
    Escondido, CA (near San Diego)
    Posts
    285

    Re: Concrete Decking Issue!!

    I agree with eggman -- if you can see it underneath, it should be torn out. Might be difficult to tell, though.

    There are testing methods (similar to an untrasound) that will give a rough depth of the rebar, but the testing might be more expensive than the deck (it is cool technology, though).

    If you cannot tell if the bar is on the bottom or not, I believe you'll see the evidence pretty fast in the form of cracking. What is the spacing of the cut or tooled shrinkage joints?

    Steve
    Pool: 625 SF Free-Form In-Ground Shotcrete Pool w/7.5' dia spa.(8 jets), 24" raised bond beam (22,500 gal)
    Pentair Equip: Intelliflo VF Pump, MasterTemp 400 Heater, IC40 SWG, Quad DE 100 Filter
    Automation: IntelliTouch i7+3 (+ extender panel), 6 Jandy Automated Valves (S, R, Spa Bypass, Solar, Cleaner, Spillway)
    Other: 75% Solar, Kreepy Kruiser Cleaner, Tan Hip-Hop Diving Board (a bit curved) on 606 Cantilever Base (SR Smith)
    Links: [TFP Pool Build Thread] - [TFP Landscaping Thread]

  4. Back To Top    #4
    el duderino's Avatar
    Join Date
    Jun 2008
    Location
    Austin, TX
    Posts
    83

    Re: Concrete Decking Issue!!

    The decking area isn't that big, and the plan is to put stone over it, so they didn't put any expansion joints. They're removing the forms as we speak, so I will attempt to try and see if I can tell where the rebar is.

    If I can't my suggestion would be to break up a very small section and see. I would be willing to pay to have that done and replaced IF I'm wrong. Otherwise, I need to propose something.

    I'm waiting to hear what the PB is going to do or suggest. I'm hoping they take care of this without me having to push the issue.

    For once in my life, I would be very happy to be proven wrong!
    Our pool- (in process)
    38x15 Free Form Gunite (3.5'-8'), 26' Negative Edge and 7' Negative Edge spa with blower, Midnight Blue Diamondbrite, AquaLogic PS-8 control, Goldline Salt Chlorine Generator, 1.5hp Pentair 2 speed pumps (2), Pentair DE Filter, Pentair 400k BTU Heater, and BlackMaxPolaris 280 cleaner with Hayward booster pump

    build diary

  5. Back To Top    #5
    Henry Porter's Avatar
    Join Date
    Nov 2008
    Location
    Sweden
    Posts
    604

    Re: Concrete Decking Issue!!

    4" it's around 100mm that is a pretty thick cast.
    If you gonna put a material on the surface you won't have to worry about cracking of the surface.
    I'm not an expert on this but to my knowledge there shoulden't be any problem if you not gonna load the edges of the deck with much force like a building of some sort. If you would do that you could experince stretching in the top of the cast.
    Otherwise it's just the the ground pressure that not gonna make any problems for you.
    It's a drag that they can't do the job carefully the way they should.
    Inground concrete pool 14600 gallons,Pentair Whisperflo 3/4HP WFE-3, Hayward swimclear 420sq ft
    Zodiac LM3-24 SWG, Dolphin Diagnostic poolrobot, Heatpump Gullberg&Jansson 13,8KW, TF testkit.

    Seen a shooting star tonight And I thought of you You were trying to break into another world A world I never knew
    I always kind of wondered If you ever made it through Seen a shooting star tonight And I thought of you

  6. Back To Top    #6
    el duderino's Avatar
    Join Date
    Jun 2008
    Location
    Austin, TX
    Posts
    83

    Re: Concrete Decking Issue!!

    Thanks for the replies.

    Like I said, there is a possibility they did their job right. I'm just trying to determine what needs to be done to make sure of it and what to do if they didn't.

    I plan to talk to the PB tomorrow, so any more advice is much appreciated.
    Our pool- (in process)
    38x15 Free Form Gunite (3.5'-8'), 26' Negative Edge and 7' Negative Edge spa with blower, Midnight Blue Diamondbrite, AquaLogic PS-8 control, Goldline Salt Chlorine Generator, 1.5hp Pentair 2 speed pumps (2), Pentair DE Filter, Pentair 400k BTU Heater, and BlackMaxPolaris 280 cleaner with Hayward booster pump

    build diary

  7. Back To Top    #7
    tsunami's Avatar
    Join Date
    Sep 2008
    Location
    Oceanside, CA
    Posts
    138

    Re: Concrete Decking Issue!!

    Quote Originally Posted by el duderino
    Like I said, there is a possibility they did their job right. I'm just trying to determine what needs to be done to make sure of it and what to do if they didn't.

    I plan to talk to the PB tomorrow, so any more advice is much appreciated.
    Like you, I'd definitely be concerned about it and let the PB know how you feel. Was there anyone else there that you could ask if they raised it? Why would they go through the trouble of putting in all the rebar and not follow thru with the final step of setting it in place and risk the chance of having to do it over?

    I've seen some concrete pours where they don't block it up, but instead, as they pour the concrete over it, they lift the rebar to set it in place as they go. Maybe that's how they did it.
    40 X 26 Free Form Pool with attached 9 X 7 Spa raised 18" with 8 Jets and Spillover, and an Art Rock Waterfall/Grotto with accent rocks, 26,000 gallons
    Intelliflo VF-3050 for Pool, VS-3050 for Spa Jets, VS-3050 for Waterfall/Grotto, Quad DE 80, 400K BTU Mastertemp, Intellitouch i7+3 w/ iS10 10 Function Spa-Side Remote, Intellichlor IC40 Salt Chlorinator, Telephone Remote, 2 Intellibrites for Pool/ 1 for Spa, Solar Panels on 2 story Roof w/ 75% coverage
    Pebble Tec Tropical Breeze Tsunami's Pool Build

  8. Back To Top    #8
    el duderino's Avatar
    Join Date
    Jun 2008
    Location
    Austin, TX
    Posts
    83

    Re: Concrete Decking Issue!!

    I've gotta agree that they have done this enough that they should know better. Hopefully, I just missed it. The two guys that were here taking the forms down didn't speak English, so I wasn't able to ask them. At least, that's what they told me

    Talked to PB Today and she said that she would ask the guy who did it, but doesn't believe they would pour without raising it. They seem to be taking a "wait and see" attitude. She said that even if it wasn't raised, it probably won't be an issue, but if it is, even 5 years down the road, they will fix it. She also said that she's seen driveways poured before on mesh that wasn't raised and they never had any issues.

    My only fear is where will they be in 5 years? I'm not really sure how long it will take before we see signs of cracking if it was poured on top and not raised. I would be fine with wait and see if there wasn't going to be many $qare feet of $tone decking on top of the concrete!
    Our pool- (in process)
    38x15 Free Form Gunite (3.5'-8'), 26' Negative Edge and 7' Negative Edge spa with blower, Midnight Blue Diamondbrite, AquaLogic PS-8 control, Goldline Salt Chlorine Generator, 1.5hp Pentair 2 speed pumps (2), Pentair DE Filter, Pentair 400k BTU Heater, and BlackMaxPolaris 280 cleaner with Hayward booster pump

    build diary

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •