    Owner-built pool build

    Gas feeder was completed mid-March. I stubbed-up the outlet near the equipment pad, and capped the line. Timeline Total = 1d Technical I used a common trench for many utilities - my workshop subpanel feeder (2" conduit), pool heater gas feeder (1"), pool plumbing return loop (2"), and...
  2. 2 Tap.JPEG

    2 Tap.JPEG

  3. S

    Owner-built pool build

    I didn't take any pictures, but we fixed the spa. TL;DR: Installed metal lathe, and built-up mortar a few inches, then waterproofed again. Timeline Total = 2d 1 day mortar 1 day waterproof Technical Started with a string layout giving the minimum increase in wall thickness (the greatest...
  4. S

    Owner-built pool build

    Tiling has started, which I'll be posting an update on once completed. But we've run into an issue. In some areas, the spa venturi's are closer to inside wall - leaving only ~1/2" between the front of the niche and gunite wall. The venturi niche itself is ~2" long. Even at the shortest length...
  5. Niche space insufficient.JPEG

    Niche space insufficient.JPEG

  6. Niche good.JPEG

    Niche good.JPEG

  7. S

    Owner-built pool build

    The pool has been paused since gunite was shot (12) days ago, while I work on the foundation for the workshop. I expect to start trenching the pool plumbing, natural gas, and main electrical subpanel next week. I'm about (1) week ahead of schedule, and nearly right-on budget (despite inflation...
  8. 10.1 Complete.JPEG

    10.1 Complete.JPEG

  9. S

    Owner-built pool build

    Gunite was done (2) days after the rebar inspection passed (about 12 days ago). Timeline: Total = 1d Technical: The crew started by checking & correcting all the rebar, formwork, and dims. They also pulled metal layout lines to mark bond beam, ledge, etc. Throughout, we discussed: bond beam...
  10. 9 Complete.JPEG

    9 Complete.JPEG

  11. 15 Finished.JPEG

    15 Finished.JPEG

  12. 13 Finished.JPEG

    13 Finished.JPEG

  13. 2 line layout.JPEG

    2 line layout.JPEG

  14. S

    Owner-built pool build

    I sub-contracted the pool rebar, in order to move quickly from excavation --> gunite. Timeline: Total = 1/2d Technical: Sub laid down masonite on top of pea gravel to give an easier work surface, and to lay spacer bricks on. Before sub arrived, I leveled all plumbing & electrical, and tied...
  15. 6 complete.JPEG

    6 complete.JPEG

  16. 3 complete.JPEG

    3 complete.JPEG

  17. S

    Owner-built pool build

    I also had difficulty sourcing. I used a couple of apps to do so, here's the final playlist: Equipment Supplier Cost Pool light Florida Sunseeker $508 Spa light Florida Sunseeker $497 Pentair CCP520 filter FB Marketplace (used) $400 Flowvis FV-2 Amazon $112 Pentair Intelliflo Amazon...
  18. S

    Owner-built pool build

    Rebar was completed a day early, and has already passed inspection. Gunite is scheduled for tomorrow, which is 8d since excavation began. I will create a separate post about the rebar and gunite (together). The post is concerning plumbing rough-in. Timeline: Total = 4d Returns = 1/2d Spa...
  19. 7 Spa.JPEG

    7 Spa.JPEG

  20. 2 Spa.JPEG

    2 Spa.JPEG

  21. 2 Skimmer bond.JPEG

    2 Skimmer bond.JPEG

  22. 1 Skimmer bond.JPEG

    1 Skimmer bond.JPEG

  23. S

    Owner-built pool build

    I've been simultaneously doing the electrical and plumbing underground. This post concerns electrical underground, which is complete. Timeline: Total = 1/2d Technical: Only the spa and pool light niche's were in-scope. I marked the pool niche vertical location w/ a spray mark, then excavated...
  24. 5 Spa niche.JPEG

    5 Spa niche.JPEG

  25. 4 Pool niche.JPEG

    4 Pool niche.JPEG

  26. 20220212_174015.jpg

    20220212_174015.jpg

  27. S

    By Owner in Phoenix: started up!!

    Your first equipment picture shows a tee off the pump w/ a FPT bushing. What's that for?
  28. S

    Owner-built pool build

    Excavation over the weekend. I've started some of the underground parallel to finishing a bit of formwork & excavation clean-up. Timeline: Total = 3d+ Excavation = 2d+ Formwork, stairs, base = 1d Technical: Transit level was set and not moved throughout. Every day I confirmed grade from the...
  29. Excavation wip