@AQUA~HOLICS thank you so much as always. I added your latest nuggets of wisdom to my shotcrete checklist.
Here's an update with a few pics
My shy guy (return) is now out and proud and past the rebar, not very far, but looks like far enough (I hope).
While the plumber was here I asked about the skimmer area and he said they understand what I was pointing out but commented that they have not run into any issues because of plumbing, it's more about the shotcrete company. Yea, blame the other guy, I thought. I said shotcrete applicator skills is important but no need to make their job more difficult. He did tie up the returns to help prevent them from getting damaged when shotcrete goes in.
Pressure holding, currently just over 40 psi (guy on ladder installing gutters).
Inspector came, didn’t see my permit hanging by the main panel and left.
I thought I saw his truck here for a few minutes and was waiting for him in the backyard or ring the doorbell. Next thing I know, the truck was gone! I called him up and he said he failed us because he didn't see the permit outside (lesson learned on that one). Thankfully he didn’t get very far before I called him so he came back. He gave us “partial approval” with “ok to gunite”.
He said wanted to see the rest of the bonding (perimeter and the run to the pad). I told him I talked to the inspection manager and he said they only needed to see the bonding connection at four equidistant points around the pool with tails. The inspector chuckled and said well if you talked to "Dave" and that is what "Dave" said than that's what "Dave" gets!
Glad I made that call.
I owe it all to
@ajw22 Thank you!!! I'm sure you saved me at least a couple days!
Best to see if you can have a phone conversation with the Inspector and ask what he will be looking for with the bonding wires.
I was interested in what he checked. He took a quick look around saw where I had the bonding, measured distance from the pool to back property line and to patio and that was it. He asked about the electric run and asked to leave the trench open for electric and gas (separate permit). He didn't even check the plumbing is holding pressure until I mentioned that "Dave" said they want to see 30psi. After our discussion he said he usually doesn't ring the doorbell unless there is a gate. How hard would it be to ring the doorbell to ask to see the permit? Aaaarrrrrgggghhhhhhhh Anyway, that's behind me now.
I've been out bending down rebar ties, have about half the pool done. That is time consuming and great opportunity to look things over closely. Most are cut pretty short. As I'm doing this I was wondering how far should I bend them and which if any are ok to leave as is. Anyway here are a few pictures of the ledge after bending down. How's it look?
While doing this I found the rebar guy didn't install the #4 @ 3" o.c. vertical as required per a detail on the engineering. This is only for a small section for my right column where the depth is over 5'. I don't know how many times I have to bring this up, but it doesn't seem to matter. I just have to watch it and catch those details. When they first bid my job they based it off a standard design for 30psf (that's fine I didn't have engineering done). I later sent them the engineering plans and pointed out the design is for 45psf. They said the price is the same. I asked them to double check it and they increased the price accordingly. When they started rebar on Friday I mentioned the #4 rebar to the owner and the rebar guy and they both said they would do that the next day (Saturday). I figured all good and didn't notice until I'm bending rebar ties. They said they would fix it Thursday. Glad I didn't pay them yet! I've been doing all cash deals to get discounts (ranging from 3 to 6%) and was scheduled to pay today.
Shotcrete lined up for next Friday with a site meet this Thursday. Electrician this Friday. Will call for rough electrical Friday for a Monday inspection.
I still need to nail down my gas contractor and get that permit applied. It might take until the end of this week. Trying to coordinate gas between my pool work (future heater and fire bowls) and my backyard contractor (fire pit and outdoor kitchen). This should save me some $$$ and even if I don't save anything I can hopefully avoid any issues and the inevitable finger pointing headaches between two different gas contractors.
Getting close! Even though I've already reviewed all of the rite of passage links I'm sooooo looking forward to my own set of links from
@kimkats!
As mentioned above, I'm attaching my shotcrete checklist I've assembled. It's a little rough, but is there anything else to add?
@Newdude I'm
the iOS posting hack!!!
Did I say how much