    For those of you that have concrete decking/patios - do you have cracks? How long did it take before they appeared? Ours was finished earlier this year and we had cracks and flaking within two weeks. Superintendent said it was normal - more and more are showing up. We had a new patio poured at our previous house and never saw a crack even after two years. Any ideas?
    Finally Done! - 21x34 IG, SWCG, depth - 3.6 - 4.6 - 6.6, Pentair IntelliFlow 3050 vs+svrs, 60 sq ft Pentair DE Filter, 400k BTU Heater, Polaris 280 w/.75 hp booster pump, Pentair EasyTouch wireless, 38 sq ft raised spa, wet edge Barbados quartz finish - ODK w/36 in Napoleon grill

  2. Back To Top    #2

    Join Date
    Jun 2012
    western NY

    Re: Concrete decking question

    No way there should be cracking and flaking after two weeks. The concrete was not finished or cured properly if that is happening. Part of the problem was they had too much water in the mix which (second part) they let evaporate out. The concrete should have been sealed as soon as the sheen went off of it.
    Unknown make 18' above ground (bought used in 1999) Sparco sand filter. Hayward 100,000 BTu heater. 2 speed pump

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts