    Planning deck..any lessons learned to share

    Hey all,
    Have a 30' pool and am planning a half wrap around 3' wide with a ___x___ deck for a table and lounge chairs. Anyway, I'm looking for lessons learned that you may have done different had you known what you know now...or even the, "I'm glad I did it that way" ideas.

    Some first thought ?'s"
    - should I go over the rail or under? Thinking under in case I ever need to remove a top rail or replace liner.
    - Wood or composite? I like composite, but is it too hot poolside...

    Thanks,
    Tim

  2. Back To Top    #2
    dmanb2b's Avatar
    Join Date
    Apr 2009
    Location
    NY
    Posts
    3,728

    Re: Planning deck..any lessons learned to share

    I'm biased, but I would go flush with the top rail. I used Trex Accents in Saddle. The heat in year 1 was bearable, but much better now (yr3) as the color will fade a bit. Composite is not maintenace free and will need to be bleached/scrubed at least annually.

    A 30 ft round is rather large to wrap. Ours is a 24ft and the best I could do is 1/4 wrap and focused on having a large area fro the kids and friends to chill. Below is a pic of my drawing and the deck when it was completed, for reference. Certanly not a stunner, but it serves our purpose











    24'x52" AGP (13,500 Gallons), Intex SWG, (2)Solar Bear 4x20 panels, Hayward S220T Filter, 1/2hp Pentair Superflo

    Pool School, TFTestKits, Pool Calculator

  3. Back To Top    #3

    Re: Planning deck..any lessons learned to share

    I second the flush to the top rail. If you go under and the deck settles or the wood shrinks, there is gap for toes to get caught in. (been there - done that). This deck was already connected to the house, then the pool was installed. This left me with no choice but to add steps. The top one is flush with the top rail. It is wood due to the $ of composite.
    Attached Images Attached Images
    30' Diameter Above Ground Pool, 20,100 gallon,
    Sand Filter, 1.5 hp Pump

  4. Back To Top    #4

    Join Date
    Jul 2011
    Location
    Walnut Creek CA
    Posts
    124

    Re: Planning deck..any lessons learned to share

    Thanks for this post - I'm planning my deck at the moment and was going to sit the deck just under the top rail... makes sence with the toes.

  5. Back To Top    #5
    BigT8600's Avatar
    Join Date
    Aug 2011
    Location
    Shreveport, LA
    Posts
    53

    Re: Planning deck..any lessons learned to share

    I'm also building a deck. the pictures are very helpful if anyone else has some to share.

  6. Back To Top    #6

    Join Date
    Jul 2011
    Location
    N. Ga Mountains
    Posts
    151

    Re: Planning deck..any lessons learned to share

    We just finished our deck...We went just under the top rail so that we could easily put the cover on. I don't have little ones and haven't had a problem with toes, yet...hope I never do. I like having a lot of deck to pool space so that several people can pull up a chair poolside. When I am in the pool and guest don't wish to swim they are still able to sit at the edge and chat. Our's is wood as $'s are scarce . I wish we could have gone bigger but again we can add on later. Love the steps that come down right near the pump so that it is quick and easy for maintenance. The one pic of the entire deck is covered with leaves as it was just after a storm. Also this deck joins our upper deck by going up 4 steps. Our yard is on the top of a ridge and it slopes down in front back and sides. Many people said I couldn't do a pool but as you can see...we did. I know you will enjoy the deck, makes your pool so much more useable![attachment=2:2dm3j2pl]P1010105.JPG[/attachment:2dm3j2pl][attachment=1:2dm3j2pl]P1010107.JPG[/attachment:2dm3j2pl][attachment=0:2dm3j2pl]P1010078.JPG[/attachment:2dm3j2pl]
    Attached Images Attached Images
    33 ft round x 52", vinyl
    Hayward 1.5 hp pump
    sta-rite 2.18ft ,200 lb sand filter
    24500 gal.
    Hayward Salt & Swim3

  7. Back To Top    #7

    Join Date
    Jul 2011
    Location
    Walnut Creek CA
    Posts
    124

    Re: Planning deck..any lessons learned to share

    More deck pictures please!

  8. Back To Top    #8
    cramar's Avatar
    Join Date
    Nov 2010
    Location
    Sault Ontario
    Posts
    1,143

    Re: Planning deck..any lessons learned to share

    - Composite is expensive but wood products will require significant more maintenance if you hope to achieve the maximum lifespan, and wood deck maintenance is a pain, if you can afford composite I'd say go with that
    - if your area gets hard winters remember that when you locate the deck boards along the edge of the pool, you'll need a bit of room in case the frost moves things around a bit
    - confirm the height of your deck the best you can ahead of time and see if you can get it to match the same height as good stock stair stringers, cutting stringers isn't extremely difficult but I think it's a pain in the you know what, if good solid prefab stringers will work I'd go with those anytime but they have to match your top board height
    - make sure you plan out where the pump and filter will go and make sure your deck doesn't bloc access to them
    - personally I wouldn't go over the rail, mine is flush and I like that, I also like the under the rail look as well. Over the rail is good as it won't allow people to inadvertently stand on the rail, if you go over the rail make sure you plan for someway of reasonably getting at the rails should you need to
    - go as large as you can, all the goodies that go along with a pool eat up deck space quickly

    Planning is #1, good planning where you've gone over things several times will pay off big time when you go to build.
    Also, if municipal bylaws are in play make sure your fully versed in those, local building dept's should help you.

    Good luck - show some pics when your done!!

    PS: Here's a link to my construction pics, hopefully it provides something useful for you.
    one-man-one-pool-and-one-deck-agp-pics-t37172.html
    20' X 54" Sharkline Matrix Resin AGP, 9400 Gallons, Sta-Rite 1 HP Dynamo Pump, 150 lb Pentair Sand Filter, Gorilla Pad,
    Foam Cove, Taylor K-2006 kit, BBB method, 8'X20' Fafco Sunsaver Hard Plumb, DIY Fountain, Margarittaville Fiji


    My Build: one-man-one-pool-and-one-deck-agp-pics-t37172.html
    My Build 'To-Do' List for other DIY'ers: my-pool-build-list-t40249.html?hilit=list

  9. Back To Top    #9
    johnnysnok's Avatar
    Join Date
    Feb 2011
    Location
    South Jersey
    Posts
    190

    Re: Planning deck..any lessons learned to share

    I went with Composite Timber Tech and went under my top rail.
    Both wood and composite get warm and they both need to be power washed in the spring.
    Maybe build in some seating while you are building your deck.
    Dough Boy 12' x 24' Oval
    Wedding Cake Steps
    1500 SF Timber Tech Composite Decking

    Video of my pool and retaining wall....Above Ground Pool Ideas - YouTube

  10. Back To Top    #10
    BigT8600's Avatar
    Join Date
    Aug 2011
    Location
    Shreveport, LA
    Posts
    53

    Re: Planning deck..any lessons learned to share

    Good Stuff! Looks like yall are either contractors or have been DIY'ing for a long time! This is my first house and I've remodeled my kitchen and done all kinds of work but never built a deck! I think with some planning and not rushing it, i can make something decent.

  11. Back To Top    #11
    linda1's Avatar
    Join Date
    Mar 2010
    Location
    Western Pa.
    Posts
    295

    Re: Planning deck..any lessons learned to share

    My advice is: It takes longer and more money than planned!! I have a 30ft round and we decided to put a 3 foot splash deck completely around ours. We started at the end of last summer and we still haven't finished it. We made it level with the rails with a small gap for the winter cover to fit through. It is very amature work! Once we get this finished, we plan to add more deck space to connect to the existing deck and pavilion.

    outer edges need cut to even it up.


    We removed the center rails on pavilion facing the pool and will add deck between the pool and pavilion with steps to the splash deck.

    This grass area will be all deck and where we will place the steps. Haven't figured out what to use for railing and sides.
    30 ft. round Conquest agp, 19,800 gal; Pentair Easy Clean 1 hp DE EC60 filter system
    Hayward H250N gas heater; TF100 Test Kit
    2 Fafco 4x20 sunsaver solar bear solar panels
    Dolphin E 10 ~ Zoomerang slide
    Majestic 8000 Above-Ground Pool Step

  12. Back To Top    #12

    Join Date
    Jul 2011
    Location
    West Monroe, La
    Posts
    67

    Re: Planning deck..any lessons learned to share

    Make sure you plan for liner change, that was one of the key factors in my deck planning, if and when the liner has to be replaced how you have deck around the edge pool matters - the guys that helped me put my pool up say the biggest mistake some people make is not allowing for liner replacement.
    27'x54" Matrix Resin - 200lb Pentair sand filter - 1.5hp Pentair optiflow 2 speed pump - Aquatrol SWG - Gorilla Pad

  13. Back To Top    #13
    johnnysnok's Avatar
    Join Date
    Feb 2011
    Location
    South Jersey
    Posts
    190

    Re: Planning deck..any lessons learned to share

    I have actually had mine replaced twice with no problems.
    Dough Boy 12' x 24' Oval
    Wedding Cake Steps
    1500 SF Timber Tech Composite Decking

    Video of my pool and retaining wall....Above Ground Pool Ideas - YouTube

  14. Back To Top    #14

    Re: Planning deck..any lessons learned to share

    Thanks everyone, I appreciate the comments and pics. You are all doing some very nice work.
    How do those of you with the deck going over the top get a cover on in the winter?
    I guess by going under the top rail and enforcing a no jump policy could be effective...and toes left will be fed to the chickens.

  15. Back To Top    #15
    dattia's Avatar
    Join Date
    Jun 2008
    Location
    West Chester, PA
    Posts
    511

    Re: Planning deck..any lessons learned to share

    My deck builder convinced me to go over the top rail. It has been a month so far and I have no regrets (I imagine that if I ever have to replace the liner, I will have to remove the first few boards of the decking, but that would be easy enough to do.) I have composite under foot, it does get hot, but I splash a little water on it and that cools it off nicely... I just love the thought of NO splinters. To keep my costs down, I did go with traditional wood handrails and balusters which I plan to stain after some time.

    I have tried to attach pics but I get this message... The image file you tried to attach is invalid.
    27' round AG
    Hayward Matrix 1 1/2 HP Pump
    Hayward S210T Sand Filter

  16. Back To Top    #16

    Join Date
    Jul 2011
    Location
    Walnut Creek CA
    Posts
    124

    Re: Planning deck..any lessons learned to share

    I'd love to see those pictures if you can figureit out...

  17. Back To Top    #17
    dattia's Avatar
    Join Date
    Jun 2008
    Location
    West Chester, PA
    Posts
    511

    Re: Planning deck..any lessons learned to share

    Not the best pictures, but I think you can get the idea. One little area of the trim had pulled away from the front, but has since been fixed.

    [attachment=0:37bga3yd]deck3.jpg[/attachment:37bga3yd]
    [attachment=1:37bga3yd]deck.jpg[/attachment:37bga3yd]
    Attached Images Attached Images
    27' round AG
    Hayward Matrix 1 1/2 HP Pump
    Hayward S210T Sand Filter

  18. Back To Top    #18

    Join Date
    Jul 2011
    Location
    Walnut Creek CA
    Posts
    124

    Re: Planning deck..any lessons learned to share

    dattia - how do you like the boards over the side wall? looks good for jumping off and less time in construction.

  19. Back To Top    #19
    dattia's Avatar
    Join Date
    Jun 2008
    Location
    West Chester, PA
    Posts
    511

    Re: Planning deck..any lessons learned to share

    I'm actually glad that I gave in to the contractor. I have to admit it has been nice sitting on the edge without the rail under my legs and it has been easy for the dog to jump in from the edge, although I don't imagine the rail would have bothered him much. It is a very strong edge and there is no weight on the top rail at all. I haven't quite figured out how I will handle the winter cover but I am sure it won't be a big deal.

    I have walk in steps that should be mounted to the deck, however, I don't think that I am going to mount them at all. They are easily moved to allow for vacuuming, changing out the water underneath them... and the best part... we can move them to the center of the pool to be home base for the dog when we are playing with him (it prevents him from taking the toys out of the pool that we would then have to retrieve. )
    27' round AG
    Hayward Matrix 1 1/2 HP Pump
    Hayward S210T Sand Filter

  20. Back To Top    #20

    Join Date
    Jul 2011
    Location
    Walnut Creek CA
    Posts
    124

    Re: Planning deck..any lessons learned to share

    I'm wondering how the contractor was able to give that last board enough support for someone to be able to stand on... would it be too much to ask if you to get a picture of that area from below? I'm not keen on the idea of my kids (and other bigger kids) constantly jumping off the rail in the same spot time after time.