Gunite Question

Mine was about 70 days between Gunite and Plaster. But they did the waterline tile and the coping much sooner.

Part of my Schedule:

Day12 1/21/11 Gunite
Day13 >>>Water Gunite
Day14 >>>Water Gunite
Day15 >>>Water Gunite
Day16 >>>Water Gunite
Day17 >>>Water Gunite
Day18 >>>Water Gunite
Day19 >>>Water Gunite
Day20 >>>Water Gunite
Day21 >>>Water Gunite
Day22 1/31/11 Tile around pool and spa >>>Water Gunite
Day23 2/1/11 Fix problem areas in the tile >>>Water Gunite
Day24 2/2/11 Level and Compact Decking, Fire Pit and BBQ areas
Day25
Day26
Day27
Day28
Day29 2/7/11 Prep for Coping and patio footings
Day30
Day31
Day32 2/10/11 Pour Coping
 
Thanks guys. Heard from my PB last night. If the weather cooperates - in PA it's been raining almost every day for the past 6 days - final plumbing and waterline tile will be getting done next week.
 