    Quoted/Contract Price vs Actual/Final Price

    I'm concerned about the final cost of our (yet to be determined) pool build and would like to hear of other's experiences so I can avoid any unexpected surprises.

    Was there a great difference between the price you were quoted and what you actually paid when it was all said and done? I'm not talking about making upgrades along the way. My concern is for unforeseen things. We don't have extra thousands laying around to pay at completion. Just want to be prepared.

    Thank you!

    Denise
    Denise-TFP Guide
    IG 13.6x30 gunite, Radiant Fusion Topaz, 3.6/5.6/4, 14100 gal, 2 skimmer, 4 Hayward LED lights (pool & spa), Hayward Echostar VSP, 2 future fire bowls, raised beam wall w/ scuppers,7x7 raised spa, DE Progrid70, SWG Hayward Goldline, OmniLogic, Hayward 400K BTU heater, stamped colored deck, Dolphin Discovery robotic cleaner, TF100 test kit, Newbie in Bixby Oklahoma

  2. Back To Top    #2

    TFP Guide

    chiefwej's Avatar
    Join Date
    Jun 2011
    Location
    Tucson
    Posts
    2,853

    Re: Quoted/Contract Price vs Actual/Final Price

    In my case the total was about 5% more than the original quote. All the up charges were the result of change orders that I had signed off on during the build. I could have held it right to the quote, but we decided to tile the spa benches, add some additional decking, and make a couple other minor changes. Some were actually no cost changes, but others had a cost. In every case we knew exactly how much addition cost we were adding. It was spelled out in every change order.
    chiefwej
    Tucson, AZ
    16x36 rectangular (19k) Pebble Tec play pool/spa, Pentair Intelliflo VS 011018, Super II 2hp (spa), Aqua Rite T-15 SWG, Pro Grid 60 DE, Hayward H400 & Heliocol Solar heating, A&A infloor system, fill water w/high CH and TA, 50 ppm borates,TF-100 test kit

  3. Back To Top    #3
    bdrums's Avatar
    Join Date
    Jul 2015
    Location
    The Woodlands, TX
    Posts
    244

    Re: Quoted/Contract Price vs Actual/Final Price

    The way it worked for us was that we signed the contract with the builder. The contract stated the payment schedule. We then took that contact to the bank and finalized the loan. The bank cut us checks for exact amounts on the payment schedule. That is what the builder will get paid.

    Any change orders are subject to increase the cost. Things like upgrading the plaster surface, pumps, etc.

    Where we found we had to set aside extra was in getting our yard, irrigation and fencing back to normal after the builder leaves. They said they would do all of that for us, but it would be line items in the contact and we would be better off having that done ourselves afterward because he would just be the middle man and probably hire the same contractors we would. So why pay him?

    Irrigation repair will probably be the biggest expense for us. Around $2K - $2.5K to rerun the zones and repair the valve system. New sod will be a couple hundred dollars and we can put that down ourselves. We are going to add some additional fencing on the side of the house since we have wrought iron in the front to give us a little more privacy in the back yard.

    A buddy of mine had to pay to have a power line that ran through his yard moved. Who pays for moving lines, etc is not real clear everywhere.

    You may have to do additional cleanup. Some do. Some don't. Depends on how much gunite and stone work dust get on your windows, siding, brick, fence, etc.

    Get references for your builder and ask them if there were any additional charges on the build itself. That will tell you a lot about the builder. The BBB is a great resource. I rejected a builder who had a stellar rating on the BBB and only 1 complaint. Why? His response wasn't very professional and left me with an uneasy feeling. He has a great reputation otherwise, but his response didn't sit well with me.

    Good luck. I hope this helps.

    EDIT: Forgot - the builder told us up front we would need to upgrade our gas meter. In fact, all of the builders we interviewed told us the same thing. I think that will cost $300 - $400 or so.
    Build thread
    IG Gunite w/ spa, PebbleSheen Blue Surf, 18K gallons 500sqft
    Jandy: 60 DE filter, 2.0 VS (main pump), 2.0 Flo Pro (features)
    Paramount PV3 w/ 1.5 Stealth, PDA PS6, JXi 400K NG
    Flagstone coping & wall. Stamped Concrete from BrickForm. TF-100 w/Speed Stir.

  4. Back To Top    #4
    Helen203's Avatar
    Join Date
    Jul 2015
    Location
    Annapolis, MD
    Posts
    813

    Re: Quoted/Contract Price vs Actual/Final Price

    I think you'll have a change order to two before its all done -- we have, and we're not finished yet. Examples: extra pool light ($1k), different pool tile, upgraded series ($500, plus $200 to return first tiles).
    My Pool Build (2015): inground 12K gals gunite/plaster pool, SWG, 2-speed pump, cartridge filter, gas heater, and polaris cleaner (Jandy). TF-100 Test Kit w/ Speed Stir

  5. Back To Top    #5
    Mod Squad pooldv's Avatar
    Join Date
    Aug 2012
    Location
    DFW, TX
    Posts
    23,994

    Re: Quoted/Contract Price vs Actual/Final Price

    We didn't make any changes and paid the price quoted.
    TFP Moderator
    If TFP helped you or saved you money - Become a TFP Supporter! <--Click here
    2012 build and pics, 20k gal gunite, black onyx pebblesheen, OK flagstone, IntellifoVS, cart filter w/Pleatco, IC40 SWG, Solartouch, 5 12'x4' solar panels, HP50HA heat pump, 8mil solar cover, borates, TF-100 test kit, SONOS, Doheny's Discovery Robot, hot tub on bleach

  6. Back To Top    #6


    TFP Guide

    Join Date
    Jul 2015
    Location
    Central Valley CA
    Posts
    1,073

    Re: Quoted/Contract Price vs Actual/Final Price

    We are a couple of weeks from completion and don't foresee any changes in the quoted price. Decking goes in tomorrow, next week stone work equipment set and clean up plaster week after that. When we signed the PB told us the only possible increase on their end would be if the excavator hit some had pan or a large bolder, in one case they ran into a VW Bug. Seems like the majority of the time customer changes are the biggest driver of price increases. I agree with the comment above getting the yard back under control is going to be the largest unknown expense. We have not even started on that and keep finding new more expensive things to do. Putting in a pool is like painting your living room you get it done then notice the carpet is looking a bit sad. So you replace that, now the kitchen doesn’t look so good so you start to work on that seems to never to end.

  7. Back To Top    #7

    Join Date
    Jul 2012
    Location
    Cary, NC (Raleigh)
    Posts
    64

    Re: Quoted/Contract Price vs Actual/Final Price

    Perhaps we were lucky but our entire project came in dead on budget. Granted we did a very extensive upfront review multiple times with the pool builder and concrete company and other subs (grass, fence, etc...) to prevent any un-forseen issues. I feel the more you can do upfront and stick to your plan you'll be fine. I have found and heard the budget can quickly get blown if you don't have a good grasp on the pool deck surface area, its really easy to start adding more sqft once you see those forms go up and visualize the area better.
    Granted one can never predict whats under the grass when the dig starts so there are always odd things sure....but do hope this isn't taken the wrong way, if you can't afford a few thousand for those odd things perhaps saving a bit more for a pool is wiser before starting.
    18x30 Freeform In-ground Vinyl Lined. 11,500 gallons.
    4 returns, 2 skimmers, 2 main drains.
    Hayward TriStar 1hp 2-Speed Pump. Hayward S244T Filter.Hayward Goldline Panel + SWG.
    Polaris 280 cleaner. AquaComfort 75k BTU Heatpump
    TF-100

  8. Back To Top    #8


    TFP Guide

    bmoreswim's Avatar
    Join Date
    Jul 2012
    Location
    Central MD
    Posts
    3,284

    Re: Quoted/Contract Price vs Actual/Final Price

    We did agree to an extra charge from our PB after discussing their overrun on concrete. It related to a slope issue (and other things), which obviously we all knew about, and accounted for but it was a special set of circumstances. In the end, I felt I received more value/product than I was originally expecting so the extra payment was negotiated and agreed to. Other than that, there was also one occasion that I was pleased to have the equipment very well documented with model #'s in the contract because that came in handy at one point. But also our fence and landscaping were outside of contract so those $'s were only as good as I estimated them to be.
    18'x38' Rectangle (3'-8 1/2' deep w/ diving board) - 27K gal. w/ gray plaster
    Hayward equipment (cartridge filter, 2-speed pump, SWCG, automation) View Our Build
    Coverstar automatic pool cover | StoneMakers concrete retaining wall and decking
    Spring 2013 Build | Dolphin Active 20 robot cleaner | Support TFP!

  9. Back To Top    #9
    Mod Squad YippeeSkippy's Avatar
    Join Date
    Jan 2012
    Location
    'burbs of Augusta, Georgia
    Posts
    6,461

    Re: Quoted/Contract Price vs Actual/Final Price

    Our only variable was the addition of more concrete (a MUST-absolutely don't skimp on this!) and the fill dirt required as my sloped yard had to be dealt with. We didn't know how many dump trucks of fill dirt we'd need beforehand.
    My Amazon Smile for November12K Fiberglass IG, Infinity 4000 automatic cover, SWCG, Hayward Sand Filter, Hayward 1.5 Pump, Doheny Discovery Robot, Savi Melody LED pool lights, outdoor speakers and other assorted doo-dads. Sundance Altamar Hot Tub.
    Our pool build--> Our Pool Solved Our Sloping Yard Skippy's Cheap Pool Cooler -->Skippy's New Fountain

  10. Back To Top    #10

    TFP Guide

    Nursenini's Avatar
    Join Date
    Sep 2015
    Location
    Bixby, Ok
    Posts
    2,122

    Re: Quoted/Contract Price vs Actual/Final Price

    Thanks for the input everyone. That eases my mind...
    Denise-TFP Guide
    IG 13.6x30 gunite, Radiant Fusion Topaz, 3.6/5.6/4, 14100 gal, 2 skimmer, 4 Hayward LED lights (pool & spa), Hayward Echostar VSP, 2 future fire bowls, raised beam wall w/ scuppers,7x7 raised spa, DE Progrid70, SWG Hayward Goldline, OmniLogic, Hayward 400K BTU heater, stamped colored deck, Dolphin Discovery robotic cleaner, TF100 test kit, Newbie in Bixby Oklahoma

  11. Back To Top    #11
    LongDuck's Avatar
    Join Date
    Aug 2015
    Location
    Phoenix, AZ
    Posts
    39

    Re: Quoted/Contract Price vs Actual/Final Price

    Paid not a Penny more than the contracted price.

    What it comes down to is how well you planned your pool from the start. If you start making changes halfway through, you can expect to pay thousands more in restocking fees on tile, decking, and equipment changes or additions. In our case, we're both project managers so I told the PB we would be managing the schedule closely with no scope creep as we picked everything out just as we wanted it prior to contract signing. Doing your research on what you want ahead of time saves a lot of expense later on.

    ill also add that being on site during construction will make a big difference in quality of the work performed and making sure you're getting what you paid for. For example, one section of planter area would have been oddly shaped had I not been there to see the design laid out with hoses as guides for the travertine edge. A change after the fact would have added cost to redo the decking to my satisfaction. Same for dis-colored or not batch-matching travertine which I culled during setup - before they made it onto the ground.

    Be firm with the site supervisor and you may find they'll work with you to include what you want at no extra cost. We got some stone facing tile (bark) on a raised seating area edge done for free because it was use of a material overage from the fire pit - making for a great, free upgrade in appearance. Good luck,
    July2015 New - 12,900gal IG Clorine Pool: Free Form Shot/PebbleSheen, Ceramic Waterline/Travertine Coping/Deck, Paramount PV3 In-Floor, Pentair 3050VS Intelliflo Variable (3000rpm High/1000rpm Low), Pentair Clean & Clear 420 Cartridge, Venturi Skimmer, MDX/SDX Drain, Paralevel, Rock Waterfall +3/4" Aireator, Intellibrite 5G LED, EasyTouch4, and Tab Floater.

  12. Back To Top    #12

    Join Date
    May 2014
    Location
    Massachusetts
    Posts
    155

    Re: Quoted/Contract Price vs Actual/Final Price

    One thing we did during our quote process for our renovation was try to anticipate any possible adders (like, we "might need to redo waterline tile if we have problems when we remove the existing coping" for instance - which ended up happening). For all the things we could think of we asked the PB to add them to the quote as options. If you do that you are in a better position than if you are halfway through your build and something "pops up" - at that point it's not like you're going to go get 3 more quotes to make sure the price is reasonable. So ask the PB what things might pop up during the build, and get them to add them to your quote now so you have a better idea where the cost might end up worst-case. Also, we added a few extras - mainly "oh heck, let's just do this even though it pushes our budget up more than we really wanted" kind of things - so anything you might even remotely consider adding - get the price now before you sign. Hopefully your PB would not jack the price up for late adders, but you basically lose all negotiating power once they start the project.....
    ~25000 gal IG gunite pool, built 2001 - renovated 2015
    Pebble Sheen Blue Surf + Shimmering Sea, Gemz, Classic Pool & Tile Rodio waterline
    Grey Granite Paver Deck, with TechoBloc Blu60 Smooth accent strip
    Hayward OmniLogic, UCL and CL320 LED lights, DE6020 filter, EcoStar pump, TF-100, T-15 SWG, Raypak P406A heater

  13. Back To Top    #13

    TFP Guide

    Nursenini's Avatar
    Join Date
    Sep 2015
    Location
    Bixby, Ok
    Posts
    2,122

    Re: Quoted/Contract Price vs Actual/Final Price

    Quote Originally Posted by chinatti View Post
    One thing we did during our quote process for our renovation was try to anticipate any possible adders (like, we "might need to redo waterline tile if we have problems when we remove the existing coping" for instance - which ended up happening). For all the things we could think of we asked the PB to add them to the quote as options. If you do that you are in a better position than if you are halfway through your build and something "pops up" - at that point it's not like you're going to go get 3 more quotes to make sure the price is reasonable. So ask the PB what things might pop up during the build, and get them to add them to your quote now so you have a better idea where the cost might end up worst-case. Also, we added a few extras - mainly "oh heck, let's just do this even though it pushes our budget up more than we really wanted" kind of things - so anything you might even remotely consider adding - get the price now before you sign. Hopefully your PB would not jack the price up for late adders, but you basically lose all negotiating power once they start the project.....
    Thank you! Great idea!!
    Denise-TFP Guide
    IG 13.6x30 gunite, Radiant Fusion Topaz, 3.6/5.6/4, 14100 gal, 2 skimmer, 4 Hayward LED lights (pool & spa), Hayward Echostar VSP, 2 future fire bowls, raised beam wall w/ scuppers,7x7 raised spa, DE Progrid70, SWG Hayward Goldline, OmniLogic, Hayward 400K BTU heater, stamped colored deck, Dolphin Discovery robotic cleaner, TF100 test kit, Newbie in Bixby Oklahoma