 Post subject: How long to wait before pavers?
PostPosted: July 16th, 2011, 2:32 pm 
Registered User

Joined: June 26th, 2011, 6:48 am
Posts: 69
Location: Long Island, NY
Not sure where to post this one figured I would start here.

Finishing our IG pool build next week and need to start planning the paver patios going around the pool area. My question for those of you who have gone through this already is how long to you wait for the ground to settle before starting your paver patios? We are looking at a significant investment in patio costs and I sure don't want it to start buckling two years in. I've received so much different information from the experts ranging from "go ahead and get started immediately" to "wait a year before you start" and Im trying to get some real life advice.

One thing to note is we put in a vinyl liner, concrete walled pool so there was some pretty significant excavation that needed to be done. Not to mention that ridiculously large oak tree stump that needed to be removed which caused them to pull up another 3x10 ft area behind the shallow end wall.

Appreciate any and all assistance.



_________________
25K Gallon IG Vinyl Liner w/ concrete walls True "L" 16X32X16, Hayward EcoStar VS pump, Hayward Swimclear C4030 Filter, Hayward 21104T Heat Pro Titanium Heat Pump, Hayward Aqua Plus SWG + Automation, 2 Hayward Color Logic 4.0 LED lights, Polaris 9300 cleaner. TF-100 test kit.
Offline
 Profile  
 
 Post subject: Re: How long to wait before pavers?
PostPosted: July 16th, 2011, 4:53 pm 
Special Contributor
Special Contributor

Joined: April 1st, 2007, 8:12 am
Posts: 11315
Location: Raleigh, NC
Are the pavers gonna' rest on a sand base or are you pouring any concrete?



_________________
Dave S.
Site Owner
TFTestkits owner
TFTestkits , Pool Calculator , Pool School
Offline
 Profile  
 
 Post subject: Re: How long to wait before pavers?
PostPosted: July 16th, 2011, 9:48 pm 
Registered User

Joined: June 26th, 2011, 6:48 am
Posts: 69
Location: Long Island, NY
Most likely a 4" RCA base composed of crushed gravel.



_________________
25K Gallon IG Vinyl Liner w/ concrete walls True "L" 16X32X16, Hayward EcoStar VS pump, Hayward Swimclear C4030 Filter, Hayward 21104T Heat Pro Titanium Heat Pump, Hayward Aqua Plus SWG + Automation, 2 Hayward Color Logic 4.0 LED lights, Polaris 9300 cleaner. TF-100 test kit.
Offline
 Profile  
 
 Post subject: Re: How long to wait before pavers?
PostPosted: July 16th, 2011, 11:56 pm 
Lifetime Supporter
Lifetime Supporter

Joined: January 21st, 2011, 2:27 am
Posts: 345
Location: Riverside, CA
It probably depends on the soil type and how much you had to move and fill.

My guys did my pavers at the same time as the pool. My raised Firepit area is a couple feet of fill dirt. They compacted it with the Jumping Jack and then put in the gravel and sand. Then they compacted the sand with the Vibrating compactor.

If they can install concrete right away and not have that sag/buckle I'd think pavers would be ok. I'm not in any way an expert on the subject.

I assume you will continue to get all sorts of answers :blah:



_________________
40x20 Free Form IG Pool (aprox 29,000 Gal, 140 Perimeter, depth 3'6"-7', Baja Shelf, 8x8 Free Form Spa) - Gunite Shell, Pebble Plaster Finish, Poured Concrete Coping - 3 Deep Heat Returns - Jandy LXi400 Gas Heater (400,000 Btu) - Jandy Variable Speed Pump JEP 2.0 - Jandy CL 600 Filter - HASA Liquidator - Jandy PDA 6 w/ Remote - 4x Jandy WaterColors Pool LEDs - 48" Gas Fire Pit - 6x Gas Tiki Torches - 12'x15' U-shaped BBQ Island (Firemagic Equipment)
http://www.troublefreepool.com/new-pool-under-construction-riverside-ca-t28413.html
Offline
 Profile  
 
 Post subject: Re: How long to wait before pavers?
PostPosted: July 17th, 2011, 12:08 am 
Lifetime Supporter
Lifetime Supporter
User avatar

Joined: January 6th, 2010, 10:54 am
Posts: 2458
Location: San Dimas, CA (LA County)
If your dirt is anything like mine (virtual concrete when dry) I'd wait until a couple of rainstorms have soaked things. In the meantime, just lay the pavers as stepping stones to keep feet clean.

Image



_________________
16K freeform gunite with spa; Pentair 4000 DE filter; Century Whisperflow 1 HP; Pentair Minimax heater.
Offline
 Profile  
 
 Post subject: Re: How long to wait before pavers?
PostPosted: July 17th, 2011, 12:21 am 
Registered User

Joined: August 2nd, 2010, 3:56 pm
Posts: 157
Location: MA
I had my IG, steel-walled, vinyl pool installed last fall and I decided to wait until the spring to lay my paver decking. My soil is predominantly sandy, however, alot of processed gravel was brought in to backfill the areas that were over-dug for the panel shelf. The fill was compacted as much as possible using a large excavator. I, too, received conflicting information on whether it was necessary to wait. I can tell you that when the snow finally melted and I removed the winter cover, that fill had settled a good 4".



_________________
Completed: June 2011
18' X 38' IG Vinyl, 3' - 8' depth ~ 24K gallons
2 skimmers, 2 wall suctions, 3 returns, 1.5" piping

Hayward Equipment: 1HP Tri-star 2-speed, Aqua-Plus SWG,
Star-Clearâ„¢ Plus 175 sqft cartridge filter, Colorlogic 4.0 LED

The Pool Cleaner 4X(suction)
2011 Jacuzzi J-280 Hot tub
Offline
 Profile  
 
 Post subject: Re: How long to wait before pavers?
PostPosted: July 17th, 2011, 7:48 am 
Special Contributor
Special Contributor

Joined: April 1st, 2007, 8:12 am
Posts: 11315
Location: Raleigh, NC
You will get SOME settling....no way out of it. Just how much depends on the type of soil, how much it was disturbed and a whole list of other factors so it is somewhat unpredictable.

That said, with pavers on sand, the worse case is you remove the pavers and redo the bed if the settling becomes objectionable.

So I guess if it were me I would wait because I would be willing to trade off the unfinished look for only installing them once. Your situation and particular priorities may be different.

Concrete is an entirely different situation.



_________________
Dave S.
Site Owner
TFTestkits owner
TFTestkits , Pool Calculator , Pool School
Offline
 Profile  
 
 Post subject: Re: How long to wait before pavers?
PostPosted: July 17th, 2011, 10:29 am 
Registered User

Joined: June 26th, 2011, 6:48 am
Posts: 69
Location: Long Island, NY
Thank you all for the replies as they are quite helpful in planning my next steps. Were on the North Shore of Long Island which gives us about 2 feel of rich clay topsoil and then nothing but sand underneath. Although the PB tried to keep the two apart, inevitably they get mixed together during the backfill process which leaves us with a pretty unstable mix on top.

We received several quotes for both types of underlayment: 4" concrete slab+pavers at $11-$12/ sq ft and 4" crushed RCA+pavers at $8-$9/ sq ft.

Im thinking either wait 3 months and go with the concrete or wait till the spring and go with the RCA...just need to see how long my patience holds out with artificial grass and dirt everywhere!



_________________
25K Gallon IG Vinyl Liner w/ concrete walls True "L" 16X32X16, Hayward EcoStar VS pump, Hayward Swimclear C4030 Filter, Hayward 21104T Heat Pro Titanium Heat Pump, Hayward Aqua Plus SWG + Automation, 2 Hayward Color Logic 4.0 LED lights, Polaris 9300 cleaner. TF-100 test kit.
Offline
 Profile  
 
 Post subject: Re: How long to wait before pavers?
PostPosted: July 17th, 2011, 11:31 am 
Registered User

Joined: June 26th, 2011, 6:48 am
Posts: 69
Location: Long Island, NY
In case anyones interested.....we have a running thread of our build in the "under construction" section that we have been trying to keep up to date.

new-pool-construction-long-island-ny-t35844.html



_________________
25K Gallon IG Vinyl Liner w/ concrete walls True "L" 16X32X16, Hayward EcoStar VS pump, Hayward Swimclear C4030 Filter, Hayward 21104T Heat Pro Titanium Heat Pump, Hayward Aqua Plus SWG + Automation, 2 Hayward Color Logic 4.0 LED lights, Polaris 9300 cleaner. TF-100 test kit.
Offline
 Profile  
 
 Post subject: Re: How long to wait before pavers?
PostPosted: July 20th, 2011, 1:01 pm 
Lifetime Supporter
Lifetime Supporter

Joined: February 23rd, 2011, 10:47 pm
Posts: 80
Location: Sicklerville, NJ
Better safe than sorry, as they say. I'd agree you're on the right track for 3 months for slab or else Spring. A few months wait is better than years of maybe living with something you'll kick yourself over time and again. I backfilled with RCA and still giving it a month to settle before pouring the deck.



_________________
25k gal Lazy-L, vinyl liner, poly walls, swimout spa, diving board, TurboTwister slide.
Hayward 2HP 2-spd pump, Pentair 2HP spa pump, Hayward 30" 500lb sand filter.
Goldline Pro Logic PS-8 automation/SWG. 2 LED ColorLogic 4.0. 8 Jandy deck jets. MX-8 cleaner.
Offline
 Profile  
 
 Post subject: Re: How long to wait before pavers?
PostPosted: July 26th, 2011, 7:42 am 
Registered User

Joined: June 26th, 2011, 6:48 am
Posts: 69
Location: Long Island, NY
TY for the help guys....one question on bonding. If we go with the pavers on the RCA do we still need to put in a rebar grid to tie in the ground wire running around the pool? Currently they have copper ground tied into 2 pieces of rebar coming off the top of the concrete walls as well as being tied into all the ladder and rail brackets. Does this then need to be tied into a rebar grid within the RCA? Is there an easier way to do this, such as burying some large pieces of rebar into the ground within the RCA for the pavers and tying into that rather than building a grid?



_________________
25K Gallon IG Vinyl Liner w/ concrete walls True "L" 16X32X16, Hayward EcoStar VS pump, Hayward Swimclear C4030 Filter, Hayward 21104T Heat Pro Titanium Heat Pump, Hayward Aqua Plus SWG + Automation, 2 Hayward Color Logic 4.0 LED lights, Polaris 9300 cleaner. TF-100 test kit.
Offline
 Profile  
 
 Post subject: Re: How long to wait before pavers?
PostPosted: July 26th, 2011, 9:22 am 
Special Contributor
Special Contributor

Joined: May 20th, 2007, 4:29 pm
Posts: 3053
Location: South Central NJ
You may have to put down a metal mesh. Building codes vary. Ask the local construction authority what they require.

Scott



_________________
Owner of - PoolGuyNJ LLC
Expert Pool and Spa Repairs, Renovations, and Augmentation. Helping people decide what is the right gear for meeting their needs. Expectations Set, Expectations Met, No Surprises.
Offline
 Profile  
 
 Post subject: Re: How long to wait before pavers?
PostPosted: July 26th, 2011, 10:27 am 
Lifetime Supporter
Lifetime Supporter

Joined: January 21st, 2011, 2:27 am
Posts: 345
Location: Riverside, CA
We had a big discussion about this in California (ask Spillmar). The County Inspectors changed their collective minds 2 times during my build alone.

Original 'Rule' : 2' wide border of rebar bonding grid under concrete adjacent to the pool
2' wide border of copped mesh/grid under pavers adjacent to the pool

New 'Rule' : a single copper wire of some minimum guage was sufficient under either concrete or pavers. Burried 4" deep around the entire perimeter of the pool (including the raised bond beam at the rear of my pool).

The New Rule was repealed after some big discussion with all the County Inspectors. The fall back to the Original Rule specifications.

My pool was fine, the PB installed the 2' of Rebar under the concrete and the single wire under the Pavers and along the back side of the pool.

Spillmar almost had to purchase 500 LF of copper grid :goodjob:



_________________
40x20 Free Form IG Pool (aprox 29,000 Gal, 140 Perimeter, depth 3'6"-7', Baja Shelf, 8x8 Free Form Spa) - Gunite Shell, Pebble Plaster Finish, Poured Concrete Coping - 3 Deep Heat Returns - Jandy LXi400 Gas Heater (400,000 Btu) - Jandy Variable Speed Pump JEP 2.0 - Jandy CL 600 Filter - HASA Liquidator - Jandy PDA 6 w/ Remote - 4x Jandy WaterColors Pool LEDs - 48" Gas Fire Pit - 6x Gas Tiki Torches - 12'x15' U-shaped BBQ Island (Firemagic Equipment)
http://www.troublefreepool.com/new-pool-under-construction-riverside-ca-t28413.html
Offline
 Profile  
 
 Post subject: Re: How long to wait before pavers?
PostPosted: July 26th, 2011, 9:54 pm 
In the Industry

Joined: March 2nd, 2011, 8:02 pm
Posts: 1611
Regardless of what the inspector would allow, I'd recommend a bonding grid that extends 3 feet from the pool wall. If you get any stray current, you will reduce the likelihood of it being noticeable.


Offline
 Profile  
 
 Post subject: Re: How long to wait before pavers?
PostPosted: July 26th, 2011, 10:22 pm 
Lifetime Supporter
Lifetime Supporter

Joined: January 21st, 2011, 2:27 am
Posts: 345
Location: Riverside, CA
It might have been 3' insead of 2' :/



_________________
40x20 Free Form IG Pool (aprox 29,000 Gal, 140 Perimeter, depth 3'6"-7', Baja Shelf, 8x8 Free Form Spa) - Gunite Shell, Pebble Plaster Finish, Poured Concrete Coping - 3 Deep Heat Returns - Jandy LXi400 Gas Heater (400,000 Btu) - Jandy Variable Speed Pump JEP 2.0 - Jandy CL 600 Filter - HASA Liquidator - Jandy PDA 6 w/ Remote - 4x Jandy WaterColors Pool LEDs - 48" Gas Fire Pit - 6x Gas Tiki Torches - 12'x15' U-shaped BBQ Island (Firemagic Equipment)
http://www.troublefreepool.com/new-pool-under-construction-riverside-ca-t28413.html
Offline
 Profile  
 
 Post subject: Re: How long to wait before pavers?
PostPosted: July 27th, 2011, 10:03 am 
Registered User

Joined: June 26th, 2011, 6:48 am
Posts: 69
Location: Long Island, NY
TY guys for the replies. Not doing pavers till the spring but now I understand what needs to be done and can incorporate into my planning. Will also speak with local building code department and see what particulars I need to abide by.



_________________
25K Gallon IG Vinyl Liner w/ concrete walls True "L" 16X32X16, Hayward EcoStar VS pump, Hayward Swimclear C4030 Filter, Hayward 21104T Heat Pro Titanium Heat Pump, Hayward Aqua Plus SWG + Automation, 2 Hayward Color Logic 4.0 LED lights, Polaris 9300 cleaner. TF-100 test kit.
Offline
 Profile  
 
 Post subject: Re: How long to wait before pavers?
PostPosted: July 27th, 2011, 7:31 pm 
In the Industry

Joined: March 2nd, 2011, 8:02 pm
Posts: 1611
Check this post for an example of what can happen when there is stray current and no bonding grid.

Stray current is not common, and having the grid won't absolutely assure that no one would feel stray current if there happens to be one, but I feel that it is best to have one.


Offline
 Profile  
 
 Post subject: Re: How long to wait before pavers?
PostPosted: July 28th, 2011, 7:23 pm 
Registered User

Joined: June 26th, 2011, 6:48 am
Posts: 69
Location: Long Island, NY
Totally agree James and TY. Will certainly be bonding a grid under my paver build.



_________________
25K Gallon IG Vinyl Liner w/ concrete walls True "L" 16X32X16, Hayward EcoStar VS pump, Hayward Swimclear C4030 Filter, Hayward 21104T Heat Pro Titanium Heat Pump, Hayward Aqua Plus SWG + Automation, 2 Hayward Color Logic 4.0 LED lights, Polaris 9300 cleaner. TF-100 test kit.
Offline
 Profile  
 
 Post subject: Re: How long to wait before pavers?
PostPosted: August 14th, 2011, 5:22 pm 
Registered User

Joined: June 26th, 2011, 6:48 am
Posts: 69
Location: Long Island, NY
Update: thankfully made the decision to wait. Torrential rain the last two days and we have some areas that have sunk close to a ft around the outside pool walls! Have read many users on this forum who back filled with pea-gravel which is something I did not even think of doing at the time.



_________________
25K Gallon IG Vinyl Liner w/ concrete walls True "L" 16X32X16, Hayward EcoStar VS pump, Hayward Swimclear C4030 Filter, Hayward 21104T Heat Pro Titanium Heat Pump, Hayward Aqua Plus SWG + Automation, 2 Hayward Color Logic 4.0 LED lights, Polaris 9300 cleaner. TF-100 test kit.
Offline
 Profile  
 
 Post subject: Re: How long to wait before pavers?
PostPosted: August 14th, 2011, 8:10 pm 
Lifetime Supporter
Lifetime Supporter
User avatar

Joined: April 4th, 2009, 9:30 am
Posts: 3294
Location: NY
Yup...I'd wait. LI get's plenty of freeze/thaw cycles over the winter. I'd rather see that excavation work settle over the winter. We did that on our large patio unilock patio 5 years ago with a 4" compacted stone dust base and have no settling...phew. At least pavers can be reset if you do get settling vs. concrete, but is still a pain in the behind.



_________________
24'x52" AGP (13,500 Gallons), Intex SWG, (2)Solar Bear 4x20 panels, Hayward S220T Filter, 1/2hp Pentair Superflo

Pool School, TFTestKits, Pool Calculator
Offline
 Profile  
 
Display posts from previous:  Sort by  
 Page 1 of 1 [ 20 posts ] 

All times are UTC - 6 hours [ DST ]


Who is online

Users browsing this forum: No registered users and 0 guests


You cannot post new topics in this forum
You cannot reply to topics in this forum
You cannot edit your posts in this forum
You cannot delete your posts in this forum
You cannot post attachments in this forum

Jump to:  


TroubleFreePool.com The Web